Aging Inspection | 12/5/2019 | 12/5/2019 | 12/5/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 4/19/2019 | 4/19/2019 | 4/19/2019 | P | PART |
Michael Zawacki
|
|
|
Last sewer tap was just connected, starting to refill hole. Lot's of dirt and dust in parking lot, sweeper will be needed. Gary the sewer inspector is aware of what needs to be done.
|
Complaint Inspection | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PEND |
Michael Zawacki
|
|
|
Trackout from staging area onto Boise Hills Dr. Spoke with contractor and sewer inspector about clean up and installing propper crushed rock entrance.
|
Application received | | | 2/19/2019 | | |
|
|
|
|
Routing - Erosion and Sediment | 2/19/2019 | | 2/19/2019 | | DONE |
Andy J. Long
|
|
|
ESC general permit. RP provided.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2019 | | |
|
|
|
|
Telephone call | | | 2/19/2019 | | DONE |
|
|
|
spoke with john informing him this permit is ready and the fee amount due for issuance
|
Permit Ready to Issue | | | 2/19/2019 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 2/19/2019 | | DONE |
|
|
|
|