DOC - Permit Finaled | 7/14/2020 | 7/14/2020 | 7/14/2020 | P | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 6/17/2020 | 6/17/2020 | 6/22/2020 | | PASS |
Andy J. Long
|
|
|
Concrete washout container on site and properly used. No trackout to Denton. WIP on preping parking lot for paving. No corrections.
|
Aging Inspection | 4/17/2020 | 4/17/2020 | 4/20/2020 | | PASS |
Michael Zawacki
|
|
|
Work completed on outside of all duplexes. Still need driveway and landscaping. Ywo trash trailers on site. Lots of small trash on site, nothing leaving area.
|
Site Preparation | 12/4/2019 | 12/4/2019 | 12/4/2019 | P | PART |
Andy J. Long
|
|
|
Permit posted, perimeter sediment control installed on 3 sides of site. Using concrete washout bin.
Corrections needed: - after L2 is done with sewer work, install construction entrance per ESC site plan - install silt fence along Denton Street to control sediment and access to site from Denton. - clean mud out sidewalk and gutter in front of site on Denton.
Notified RP Ed w/ Perryman. Follow up inspection scheduled for next week.
L2 working in road and using staging area down street is permitted with ACHD. Will sweep road and gutters when pulling off site. Small sweeper unit for L2 onsite sweeping at time of inspection.
|
Permit Ready to Issue | | | 6/24/2019 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 6/24/2019 | | DONE |
|
|
|
|
Application received | | | 2/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2019 10:12AM
|