Site Final | 12/19/2019 | 1/3/2020 | 1/6/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 12/18/2019 | 12/18/2019 | 12/19/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PASS |
Michael Zawacki
|
|
|
Prep work for parcels is completed. No new activity. Lots are starting to overgrow and be stabalized.
|
Complaint Inspection | 5/17/2019 | 5/17/2019 | 5/23/2019 | P | PASS |
Michael Zawacki
|
|
|
No issues at site. Irrigation ditch is clean of debris, not currently flowing.
|
General Inspection | 4/11/2019 | 4/12/2019 | 4/15/2019 | P | FAIL |
Michael Zawacki
|
|
|
Trackout from pitrun deliveries. Message sent to RP.
|
Issue & PRINT permit COM | | | 4/11/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/3/2019 | | 4/4/2019 | | PASS |
Andy J. Long
|
|
|
ESC general permit approved. Valid RP.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 4/4/2019 | | DONE |
|
|
|
met
|
Telephone call | | | 4/4/2019 | | DONE |
|
|
|
Spoke with Phil to inform him the permit is ready and what fees are due.
|
Application received | | | 4/3/2019 | | |
|
|
|
|