Site Final | 2/28/2020 | 3/2/2020 | 3/2/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
Site Final | 12/19/2019 | 1/3/2020 | 1/9/2020 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/19/2019 | 12/19/2019 | 12/19/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
Site Final | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | NR |
Andy J. Long
|
|
|
Some minor work remaining. Near completion, no ESC issues observed
|
General Inspection | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP no ESC issues. Dumpster on site no loose trash, crew was putting wood scraps in back of truck. Broom attatchment on site, no trackout or dust.
|
Tracking Control | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Michael Zawacki
|
|
|
No workers on site, gate locked. Trackout has been swept up. Construction entrance behind locked gate.
|
Permit Ready to Issue | | | 5/15/2019 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 5/15/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/10/2019 | | 5/10/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site preparation required.
|
Application received | | | 4/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 18 2019 2:48PM
|