Site Final | 7/24/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 7/24/2020 | 7/24/2020 | 7/24/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
Site Preparation | 2/24/2020 | 2/24/2020 | 2/28/2020 | P | PASS |
Andy J. Long
|
|
|
WIP. Keeping a clean site. Most of work is in the ROW. Have push brooms and concrete washout pan
|
Permit Ready to Issue | | | 10/1/2019 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 10/1/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/2/2019 | | 5/2/2019 | | DONE |
Michael Zawacki
|
|
|
Valid RP needed before permit issues. Urban project.
|
Application received | | | 4/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 22 2019 4:44PM
|