General Inspection | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 4/1/2020 | 4/1/2020 | 4/1/2020 | | PASS |
Michael Zawacki
|
|
|
Exterior finished and landscaped. Avalon landscape is finishing up outside.
|
General Inspection | 1/31/2020 | 1/31/2020 | 1/31/2020 | | PASS |
Andy J. Long
|
|
|
No trackout or discharges. Vertical construciton in progress. No corrections requested.
|
General Inspection | 10/4/2019 | 10/4/2019 | 10/4/2019 | P | PASS |
Andy J. Long
|
|
|
RP on duty. No trackout. Concrete washout pan and perimeter wattles installed. Approved.
|
Site Preparation | 8/23/2019 | 8/23/2019 | 8/26/2019 | P | PASS |
Andy J. Long
|
|
|
JC with Petra
Site BMPs installed. Approved for construction. Storm drain in alley has sediment protection, perimeter wattles are staged. Preserved asphalt site access.
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 8/22/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/6/2019 | | 6/6/2019 | | DONE |
Michael Zawacki
|
|
|
RP needed. Site prep inspection required.
|
Application received | | | 5/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2019 3:07PM
|