General Inspection | 6/30/2020 | 6/30/2020 | 6/30/2020 | | PASS |
Michael Zawacki
|
|
|
Outside hangar work looks completed. Still materials and backfill laying around, no parking lot or landscaping. Area is fenced, has entrance before exiting fence and before Gowen. No issues at site.
|
General Inspection | 5/12/2020 | 5/12/2020 | 5/12/2020 | | PASS |
Michael Zawacki
|
|
|
WIP on hangar. Site has gravel acces, also has construction entrance into fenced are. All materials stored on site. Buffer out to Gowen, construction on airport outside rear perimeter fence. NBo issues at site.
|
General Inspection | 3/24/2020 | 3/24/2020 | 3/24/2020 | | PASS |
Michael Zawacki
|
|
|
Site contained. Located on airport/hanger.
|
General Inspection | 2/5/2020 | 2/5/2020 | 2/6/2020 | | CANC |
Andy J. Long
|
|
|
|
Site Preparation | 10/15/2019 | 10/15/2019 | 10/16/2019 | P | DONE |
Michael Zawacki
|
|
|
Grading has begun, work on airport grounds behind gate and fence.
|
Permit Ready to Issue | | | 10/1/2019 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 10/1/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/1/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/30/2019 | | 5/30/2019 | | PASS |
Andy J. Long
|
|
|
SWPPP/ESC plan approved. Contractor and ESC Responsible Person TBD. Site preparation inspection is required.
|
Application received | | | 5/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 10 2019 12:17PM
|