General Inspection | 6/30/2020 | 6/30/2020 | 6/30/2020 | | PASS |
Michael Zawacki
|
|
|
All work contained behind existing terminal.
|
General Inspection | 5/13/2020 | 5/13/2020 | 5/13/2020 | | PASS |
Michael Zawacki
|
|
|
Site has been stripped, vegetation starting to regrow. Some stockpiles by Lake Hazel. No equipment at site. No issues.
|
General Inspection | 3/24/2020 | 3/24/2020 | 3/24/2020 | | PASS |
Michael Zawacki
|
|
|
All work in fenced in yard behind existing building.
|
General Inspection | 2/5/2020 | 2/5/2020 | 2/6/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/14/2019 | 10/15/2019 | 10/16/2019 | P | PASS |
Michael Zawacki
|
|
|
Area has been graded, some stockpiles in center of site. Area surrounded by dessert. Some removed concrete stored in middle by loading docks, no addition to the distribution building has been done. Site is accessed from south along gravel road, site has basalt entrance.
|
Issue & PRINT permit COM | | | 5/22/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/20/2019 | | 5/20/2019 | | DONE |
Michael Zawacki
|
|
|
Needs City of Boise certified RP that will be on site with day to day control.
Site prep inspection required.
|
Application received | | | 5/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2019 1:09PM
|