General Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 | | PASS |
Michael Zawacki
|
|
|
Curbing and sidewalk in progress. Fargo will also b e closed for road work. Site not paved or landscaped.
|
General Inspection | 5/15/2020 | 5/15/2020 | 5/15/2020 | | PASS |
Michael Zawacki
|
|
|
Building exterior work almost completed. Site is all fenced off, no one can drive off road onto lot. One entrance and has gravel. No trackout, no loose trash. Tates does park in mud on there side of road.
|
General Inspection | 3/30/2020 | 3/30/2020 | 3/30/2020 | | PASS |
Michael Zawacki
|
|
|
Site is clean and contained. Some tracking onto state. Is coming from in front of Tates, tracked from in front of giant no construction parking sign.
|
General Inspection | 2/12/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Michael Zawacki
|
|
|
Sitye is contained. Fence is up so workers can't drive through lot. Rock has been brought in for stabilization. No tracking.
|
Tracking Control | 1/6/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Michael Zawacki
|
|
|
Chainlink installed around site. No one can park on dirt or go to road.
|
Tracking Control | 1/2/2020 | 1/3/2020 | 1/6/2020 | A | FAIL |
Michael Zawacki
|
|
|
Trackout. Met with foreman about getting a sweeper and maybe installing pit run around building.
|
General Inspection | 10/28/2019 | 11/7/2019 | 11/6/2019 | A | PASS |
Michael Zawacki
|
|
|
Met with Mike the foreman at site. Will watch for mud when rain starts and clean streets as needed. I suggested a man walkway and boot brush to avoid boot track, workers parking on street throughout neighborhood. Washout is full and need to be replaced.
|
General Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Michael Zawacki
|
|
|
Pad has been poured, large washout on site. Entance leading to job trailer, parking along Eugene is bare dirt. Eugene has been recently swept. Wattles installed along State st and the western edge. No workers on site at time of inspection.
|
Site Preparation | 8/12/2019 | 8/13/2019 | 8/13/2019 | A | PASS |
Michael Zawacki
|
|
|
Work started without prep inspection Wattle along perimeter, slightly trenched with stakes every 5 feet. Di bags in inlet. They brought a water truck for excavation, very close to coffe frive through. Wattle along Fargo was removed during excavation. No construction entrance, very little room and parking will be an issue.
|
Issue & PRINT permit COM | | | 7/23/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/5/2019 | | 6/5/2019 | | DONE |
Michael Zawacki
|
|
|
RP needed, site prep inspection required.
|
Application received | | | 5/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2019 1:24PM
|