Site Final | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 5/13/2020 | 5/15/2020 | 5/18/2020 | P | PASS |
Michael Zawacki
|
|
|
Met with foreman on site. Plan on setting forms and starting pours this week, will get washout before they pour. Currently hauling backfill, truck is staying on pavement. No issues at site.
|
General Inspection | 5/13/2020 | 5/13/2020 | 5/13/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/5/2020 | 3/25/2020 | 3/24/2020 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/5/2020 | 3/5/2020 | 3/5/2020 | | PASS |
Andy J. Long
|
|
|
Site infrastructure complete. No activity. No dust observed, yet no stabilization measures on open parcels.No trackout or discharges on site.
|
General Inspection | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | FAIL |
Michael Zawacki
|
|
|
Trackout onto wildwood, message sent to RP.
|
General Inspection | 10/28/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Michael Zawacki
|
|
|
Entire site slopes away from roads. Large pile of backfill on site. Future road bed graded and area staked, no workers on site.
|
General Inspection | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Michael Zawacki
|
|
|
Knife River on site doing some trenching and work at sidewalk. Equipment mobolized but not active. Site still hasn't been stripped.
|
Permit Ready to Issue | | | 8/2/2019 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 8/2/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/30/2019 | | 5/30/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan appproved. Certified RP and PD. Site preparation inspection is required.
|
Application received | | | 5/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 22 2019 1:31PM
|