Aging Inspection | 8/5/2020 | 8/5/2020 | 8/5/2020 | | PASS |
Michael Zawacki
|
|
|
No new activity. Home needs to go in for historic again.
|
General Inspection | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Michael Zawacki
|
|
|
No vertical construction. Some block work around lot has been done. Sidewalk is continuously getting dirty and then cleaned. No blowing dust, have not received any complaints
|
Conference | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Michael Zawacki
|
|
|
Talked to owner while walking dog. Have been given permission to replace backfill. Plans are in for review.
|
BMP Violation | 2/11/2020 | 2/14/2020 | 2/20/2020 | A | PASS |
Andy J. Long
|
|
|
check for gutter clean up requested on Sherman and 5th
Gutter cleaned. Still needs to improve access to site to prevent trackout. Sidewalk has been swept. RP on duty, said he will continue to work on cleaning. Waiting for backfill to be completed.
|
General Inspection | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | FAIL |
Andy J. Long
|
|
|
Sweep gutter on Sherman and mud onto of curb. Provid boot brush or shovel for mud removal by works.
|
General Inspection | 1/27/2020 | 1/27/2020 | 1/28/2020 | P | FAIL |
Michael Zawacki
|
|
|
Mud puddle on low section of sidewalk on 5th side. Mini excavator blocking sidewalk on Sherman side. Film of mud on sherman side. Some tracking from moving track steer. Pit run stored on 5th, pit run ramp on sherman.
|
General Inspection | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | PASS |
Michael Zawacki
|
|
|
Gatorguard installed around backfill. Foundation poured and home resting on it. ASlley is muddy.
|
General Inspection | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PART |
Michael Zawacki
|
|
|
Gator guard along perimeter of lot and sidewalk. Some dirt still getting on sidewalk. Alley is very messy, some from construction some is that it is bare. Boot tracking across alley from workers and people using sidewalk, no clear path across alley. No workers on site.
|
General Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | PASS |
Michael Zawacki
|
|
|
Started filling in backfill. All m,aterial between road and sidewalks has been removed. Backfill still on lot, gator guard protecting sidewalks.
|
General Inspection | 10/25/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Andy J. Long
|
|
|
check for corrections.
Perimeter sediment controls installed as requested. Sediment check bag installed in gutter. Rock chip now onsite to be used for stabilzed access from parking to work area.
Approved.
|
General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | PEND |
Andy J. Long
|
|
|
Met with RP-GC Ken.
Corrective actions to occur: - install wattle around stockpiles along 5th street sidewalk. Will need to be weighed down in areas where staking is not possible. - install wattle at low point between sidewalk and alley (NW corner of lot) to treat runoff flowing to the Sherman street gutter - install snake bag check dam on Sherman gutter - clean Sherman gutter - if stockpiles can not be backfill by end on November, will need to cover with tarps.
|
General Inspection | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | FAIL |
Michael Zawacki
|
|
|
Washout dumped on 5th.
|
General Inspection | 10/14/2019 | 10/14/2019 | 10/15/2019 | P | FAIL |
Andy J. Long
|
|
|
No ESC permit sign posted. No perimeter sediment controls on site. Loose dirt in gutter on Sherman and dirt on sidewalks.
Notified RP to schedule conference.
|
Site Preparation | 9/3/2019 | 9/3/2019 | 9/4/2019 | P | PEND |
Michael Zawacki
|
|
|
Lots of dust when track steer is operating, none when not. Sent message to RP to do some dust control. Sidewalks are getting swept.
|
Issue & PRINT permit SFD | | | 8/5/2019 | | DONE |
|
|
|
|
Application received | | | 6/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2019 11:42AM
|