Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberESC19-00814
StatusFinaled
Name MICHAEL MCHARGUE
Site Address 4620 W OVERLAND RD
Project NameANDRADE'S RESTAURANT
Customer Number 
ePlanReviewNo
Description
Grading and drainage and site utilities.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final6/16/20206/16/20206/18/2020PPASS
DetailsAndy J. Long
Temp BMPs removed. Site clean and stabilized. Approved
General Inspection6/16/20206/16/20206/16/2020 CANC
DetailsAndy J. Long
General Inspection4/29/20204/29/20204/29/2020 PASS
DetailsMichael Zawacki
Parking lot paved, curbing and sidewalks completed.
None of the grass areas have been landscaped.
No issues.
General Inspection3/9/20203/9/20203/10/2020PPASS
DetailsMichael Zawacki
Met with foreman on site. Discovered two more old drains to canal, steel plate and cement to seal them.
Masons on site doing brick at bottom of walls. Some uncontained washout from stucco, will get it clean. Has trash cleanup coming in to walk and clean site.
General Inspection2/24/20202/24/20202/24/2020PPART
DetailsMichael Zawacki
No trackout from entrance. Lotsd of loose debris at site, cardboard, styrofoam, etc. All fenced in, nothing blowing off site.
General Inspection12/5/201912/5/201912/6/2019PPASS
DetailsMichael Zawacki
Trucks on site hauling at backfill, no trackout on overland at time of inspection.
Crews on site installing vapor barrier and bar on inside of foundation, walls already poured. Washout on site but currently not accesible. Lots of trash on site, all in piles.
Area is fenced in so garbage can't blow away. Site is below grade.
General Inspection10/22/201911/6/201911/6/2019PPASS
DetailsAndy J. Long
WIP on preparing foundation. Concrete washout pan on site. No trackout or fugitive dust.

Noticed an unprotected storm drain near the gararge structure. Requested that it have sediment protection.
Site Preparation10/21/201910/22/201910/22/2019APASS
DetailsAndy J. Long
mIKE Phone #: ###-####

Building on site has been demolished and hole filled in with pit run. RP states that existing asphalt around the pit run area will be preserved other than any trenching for utilities that may be required.

Will need to have concrete washout pan, spill kit, and other pollution control measures. Drainage appears to stay onsite draining to the NE corner of parcel. Construction has not yet started.
Permit Ready to Issue  10/11/2019 DONE
Issue & PRINT permit SFD  10/11/2019 DONE
(F) Reprint permit  10/11/2019 DONE
Routing - Erosion and Sediment7/2/2019 7/2/2019 DONE
DetailsMichael Zawacki
RP Needed.
Site prep inspection required.
Application received  6/13/2019 DONE
Application submitted via PDS Online on Jun 13 2019 4:37PM