General Inspection | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Michael Zawacki
|
|
|
Parking lot paved and islands installed. Landscape crew on site.
|
General Inspection | 6/22/2020 | 6/22/2020 | 6/22/2020 | P | PASS |
Michael Zawacki
|
|
|
West end curbing completed, parking lot prepped for paving. Some stockpiles of dirt and rock in field to north. Old concrete curbs and washout ripped out and dumped in lot also.
|
Issue & PRINT permit COM | | | 3/4/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/9/2019 | | 9/9/2019 | | DONE |
Michael Zawacki
|
|
|
RP needed.
Plan narrative and map on same page, will allow for this permit, parking lot only.
|
Application received | | | 8/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2019 11:09AM
|