General Inspection | 8/5/2020 | 8/5/2020 | 8/5/2020 | | PASS |
Michael Zawacki
|
|
|
Talked with builder while at site. Pump truck on site for rear patios, will remind them to use washout. Lot is clean, no issues.
|
General Inspection | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on framing, no issues.
|
General Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 | | PASS |
Michael Zawacki
|
|
|
WIp on framing, site is clean. PJ was on site.
|
General Inspection | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Michael Zawacki
|
|
|
Foundation is completed, no work on framing. Back of lot still vegetated. Backfill on lot, no issues.
|
General Inspection | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Andy J. Long
|
|
|
Permit posted. No trackout or discharges. BMPs installed
|
General Inspection | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
Michael Zawacki
|
|
|
No current activity, some concrete walls completed, form trailer still out front. Rear has no BMPs at hillside, lower right looks like it may get all water, no issues yet.
|
Site Preparation | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PASS |
Michael Zawacki
|
|
|
Site needs washout pit lined before first pour. Stabalized walkway or drive should be installed to prevent boot tracking onto sidewalk and road.
|
Permit Ready to Issue | | | 12/10/2019 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 12/10/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 10/17/2019 | | 10/17/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site preparation inspection is required.
|
Application received | | | 9/10/2019 | | |
|
|
|
|