General Inspection | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Andy J. Long
|
|
|
WIP on site development and earthwork under the site demo permit. BLD permit not yet issued for structure.
BMPs have been installed, onsite ESC Site Preparation inspection scheduled for tomorrow.
|
General Inspection | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Andy J. Long
|
|
|
Building has been demolished. Area surround by fencing. NO activitiy. NO trackout or discharges. Will continue to monitor and will conduct ESC site prep when BLD for new building is issued.
|
Permit Ready to Issue | | | 1/10/2020 | | DONE |
|
|
|
met
|
Issue & PRINT permit COM | | | 1/10/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/7/2019 | | 11/7/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver request approved. Certified RP. Please schedule ESC site prep at time of ESC permit issuance.
|
Application received | | | 11/6/2019 | | |
|
|
|
|
Site Preparation | 8/12/2020 | 8/13/2020 | | A | |
Andy J. Long
|
|
|
RP Jack Onsite contact with CSDI Mike 2088699113
|