General Inspection | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Michael Zawacki
|
|
|
Prep work looks completed, some pipe stored on north of site. Site has been water sprayed and has hard crust. Only activity is equipment mechanics.
|
General Inspection | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PASS |
Michael Zawacki
|
|
|
Crew stilll doing plumbing trench work. Will begin roads and footings after trench work completed. Water truck on site, spraying site end of each day. No concrete work or washout on site.
|
Issue & PRINT permit COM | | | 3/13/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/11/2020 | | 2/11/2020 | | PASS |
Michael Zawacki
|
|
|
RP needed. Site prep inspection required.
|
Application received | | | 12/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 16 2019 11:48AM
|