General Inspection | 6/22/2020 | 6/22/2020 | 6/22/2020 | P | PASS |
Michael Zawacki
|
|
|
Working on tilt up walls on west building. East building has foundation completed. Large lined washout on site and used. No issues at site.
|
General Inspection | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PASS |
Michael Zawacki
|
|
|
Site is clean and contained. Western building has had foundation poured, lined washout used. Crew is on site finishing rebar on east pad. No issues at site.
|
General Inspection | 3/9/2020 | 3/9/2020 | 3/9/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on grading new pads. Site still has fill that needs t be removed. Spoke with foreman, has new permit signs and will get them put up.
|
Issue & PRINT permit COM | | | 2/27/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/12/2020 | | 2/12/2020 | | DONE |
Michael Zawacki
|
|
|
RP needed.
Talked to engineer and using same swppp as previous phase. Maps will be updated at field level.
|
Application received | | | 12/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 20 2019 4:49PM
|