General Inspection | 8/11/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on framing. No trash blown off site. All workers parked in road. Will need to keep an eye on building wrap and keep site clean.
|
BMP Violation | 6/24/2020 | 7/1/2020 | 7/1/2020 | A | PEND |
Michael Zawacki
|
|
|
Crew on site filling in backfill. Trash has been cleaned. No entrance, area has been stripped like it was prepped for rock.
|
General Inspection | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | FAIL |
Michael Zawacki
|
|
|
Remnants of trash fire on site, was left and some garbage on site. No entrance installed, Road and sidewalks dirty, Eyrie RP cleaned DIs and wasn't happy. Silt fence installed and still ok. Permit sign has gone missing. Message sent to owner, follow up scheduled.
|
Site Preparation | 6/4/2020 | 6/4/2020 | 6/8/2020 | P | PASS |
Andy J. Long
|
|
|
Dave Phone #: ###-####
Silt fence perimeter installed properly, also acts to keep work and equipment within clearing limits. Storm drain in front of project has sediment proteciton. ESC permit posted, need to install construction entrance.
|
Issue & PRINT permit SFD | | | 6/3/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/17/2020 | | 3/17/2020 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Need to provide current certified Responsible Person for project. Site preparation inspection is required.
|
Application received | | | 3/10/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 10 2020 1:18PM
|