General Inspection | 8/7/2020 | 8/10/2020 | 8/11/2020 | P | PASS |
Michael Zawacki
|
|
|
Sewer and water line work looks completed. No workers or equipment on site. No stormwater controls installed on phase.
|
General Inspection | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on sewer on SE corner of project. Dust control water truck on site, minimal workers at site. Hillsides not disturbed and buffers in place. No issues, no trackout, small trench still by entrance.
|
Site Preparation | 6/16/2020 | 6/16/2020 | 6/17/2020 | P | FAIL |
Michael Zawacki
|
|
|
No workers on site. Trackout and dirt on Barber. Some water flowing off site, not picking up turbidity due to slow velocity. Majority of water currently flowing into open trench. Sent sweeping request to Kyle.
|
Issue & PRINT permit SFD | | | 4/27/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/3/2020 | | 4/3/2020 | | DONE |
Andy J. Long
|
|
|
Certified RP listed. Site preparation inspection required prior to construction
|
Application received | | | 3/13/2020 | | |
|
|
|
|