General Inspection | 6/26/2020 | 7/9/2020 | 7/9/2020 | P | PASS |
Michael Zawacki
|
|
|
Crew on site just beginning to set lines and forms. No issues.
|
Site Preparation | 6/25/2020 | 6/26/2020 | 6/26/2020 | P | PASS |
Andy J. Long
|
|
|
Bob Phone #: ###-####
Site BMPs installed: - permit sign posted - perimeter wattles installed - back end of lot has silt fence and wattle installed. - slope vegetation undisturbed during initial grading
Bob stated concrete washout to be installed after excavation prior to foundation Approved.
|
Site Preparation | 6/24/2020 | 6/25/2020 | 6/26/2020 | A | CANC |
Andy J. Long
|
|
|
Bob Phone #: ###-####
|
General Inspection | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | PASS |
Michael Zawacki
|
|
|
Site now has permit issued and fees paid. Will need prep inspection before work resumes.
|
Issue & PRINT permit SFD | | | 6/23/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/27/2020 | | 4/27/2020 | | DONE |
Michael Zawacki
|
|
|
Site prep inspection required.
|
Application received | | | 4/9/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2020 2:47PM
|