Site Preparation | 7/20/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Andy J. Long
|
|
|
after 2pm- Ted- screened Phone #: ###-####
Bridge work to begin Monday. Most construction activity will occur during night during reduced traffic and greenbelt use.
Will work on bridge deck in phases, each section of deck being worked upon will have a containment "diaper" under deck to capture any debris or other material.
Plan is to have trucks washout back at their own facility. Pumptruck and concrete will be stationed on 9th during night. Request that spill containment/drip pans be placed under transfer area.
Provided ESC permit signs. Will use some area in library parking lot for staging. If on pavers, will have secondary containment.
Approved for construction.
|
Fees Due Hold | 6/19/2020 | | 7/20/2020 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Issue & PRINT to be Invoiced | | | 6/18/2020 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/8/2020 | | 5/8/2020 | | DONE |
Michael Zawacki
|
|
|
RP needed.
Work is above and over river, site prep required.
|
Application received | | | 4/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 20 2020 12:36PM
|