Permit Information
Permit NumberFIR00-00083
StatusFinaled
Name TREASURE VALLEY FIRE
Site Address 3115 N SYCAMORE DR
Project NameSPR GOOD SAMARITAN
Customer Number 
ePlanReview 
Description
(GOOD SMARITAN Phase's IIA, IIB & III) To perform selective fire sprinkler upgrades in meeting the facilities letter of agreement requirement on file. This permit will be for Phase's IIA, IIB & III approximately 21626 sq ft . The upgrades will be performed in the I1.1 & I1.2, portions of the building. Work to include, upgrade corridors in these areas, remodel 14 sleeping rooms 205 through 209 & 401 to 409, and restrooms within these rooms. To remodel the existing mechanical building. Fire sprinkler modification per NFPA #13 per plans, attached notes and as regulated by the fire department. BLD99-02051 *JWA*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/2/20035/2/20035/2/2003PPASS
DetailsTroy Cobbley
Inspection was finaled by 406. I am DOC finaling
DOC - Permit Finaled5/2/20035/2/20035/2/2003PPASS
DetailsTroy Cobbley
Finaled by inspector at 5/2/2003 12:14:34 PM
INSP-Final Inspection4/11/20014/11/20014/11/2001PPASS
DetailsJoe Tawney
Added by Inspector: 406 On 4/11/2001 5:51:03 PM OK for certificate of completion
Telephone call  6/13/2000 DONE
LEFT MESS THAT PERMIT IS READY
Sprinkler Plan Check6/12/2000 6/12/2000 PASS
DetailsBill Alexander
Provided revision to kitchen plans submitted 06/05/00.
Sprinkler Plan Check6/5/2000 6/8/2000 PASS
DetailsBill Alexander
Kitchen Remodeled area. Added/modified 24 heads.
INSP-Sprinkler Rough-in3/23/20003/24/20003/24/2000PPART
DetailsJoe Tawney
around 1:00 if possible jim ###-#### Ok on installation of back flow preventer outside 3/27/00 10:06:52 AM
Issue permit  2/16/2000 DONE
Inspection Record Card- Bld2/11/20002/11/20002/11/2000 DONE
Telephone call  2/11/2000 DONE
Gave amount and notified that plans were ready.kkh
Sprinkler Plan Check2/4/2000 2/11/2000 PASS
Phase one underground and overhead. 98 heads modified/added.
Miscellaneous action  2/11/2000 PASS
Plans taken to the front desk for calling and distribution
Application received  2/4/2000 PASS
Case Summary    PASS