INSP-Final Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/14/2001 4:22:47 PM
|
DOC - Permit Finaled | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 8/14/2001 4:23:09 PM
|
INSP-Final Inspection | 1/10/2001 | 1/10/2001 | 1/10/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 1/10/2001 12:34:12 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/2/2001 | 1/5/2001 | 1/5/2001 | A | PASS |
Rick Jackson
|
|
|
Mike Ham ###-#### hydro okay 1/5/2001 10:42:55 AM
|
INSP-Supply line flush | 12/29/2000 | 1/2/2001 | 1/2/2001 | A | PASS |
Rick Jackson
|
|
|
underground flush Troy ###-####
|
INSP-Supply line flush | 12/28/2000 | 12/28/2000 | 12/29/2000 | P | NH |
Rick Jackson
|
|
|
mike-- ###-#### underground supply line tried calling but received no anaser 1/2/2001 8:34:09 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/26/2000 | 12/27/2000 | 12/27/2000 | A | PASS |
Rick Jackson
|
|
|
underground flush and an overhead rough in mike Hamm ###-#### /////// r/i inspectio okay alarms not complete 12/27/2000 4:18:12 PM
|
Inspection Record Card- Bld | 11/14/2000 | 11/14/2000 | 11/14/2000 | | DONE |
|
|
|
|
Issue permit | | | 11/13/2000 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/26/2000 | | 11/13/2000 | | DONE |
|
|
|
11/13/2000 09:15:05 JWA - activity updated through activity FIRA22 from case FIR00-00602.
|
Sprinkler Plan Check | 11/7/2000 | | 11/13/2000 | | PASS |
Bill Alexander
|
|
|
|
Telephone call | | | 11/13/2000 | | DONE |
|
|
|
Copy of passed review faxed to Grinnell.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/13/2000 | | DONE |
Bill Alexander
|
|
|
|
Telephone call | | | 11/3/2000 | | DONE |
Bill Alexander
|
|
|
Copy of failed review note faxed to Grinnell
|
Sprinkler Plan Check | 10/26/2000 | | 11/3/2000 | | FAIL |
Bill Alexander
|
|
|
Proposed future rack calculations/spacing does not meet code.
|
Application received | | | 10/26/2000 | | PASS |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|