DOC - Permit Finaled | 9/7/2001 | 9/7/2001 | 9/7/2001 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 9/7/2001 2:44:32 PM
|
INSP-Final Inspection | 9/7/2001 | 9/7/2001 | 9/7/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 9/7/2001 2:43:27 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/27/2001 | 8/27/2001 | 8/27/2001 | P | PART |
Rick Jackson
|
|
|
leroy ###-#### hydro need to complete sway bracing; 911 sticker 8/28/2001 7:09:46 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | NR |
Rick Jackson
|
|
|
leroy ###-#### hydro rescheduled for 8/27/01 per Leroy of Shilo 8/23/2001 2:18:52 PM
|
Sprinkler Plan Check | 8/13/2001 | | 8/21/2001 | | PASS |
Bill Alexander
|
|
|
Revised rack/mezzanine sprinkler plans FP7 and FP8 of 10.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2001 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 8/21/2001 | | 8/21/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/21/2001 | | DONE |
|
|
|
permit ready
|
INSP-Sprinkler Rough-in | 8/10/2001 | 8/13/2001 | 8/13/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 8/10/2001 3:24:23 PM racking not complete; due to changes in the racking requested resubmittals for the changes 8/13/2001 2:51:17 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/09/2001 at 13:41:04. Contact: ###-####. earthquaking not complete; overspaced at 2nd floor near elevator and stairs; rack sprinklers not complete 8/10/2001 3:26:00 PM
|
Issue and Print Permit | | | 7/24/2001 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/23/2001 | | 7/23/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/23/2001 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/17/2001 | | 7/23/2001 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2001 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 6/1/2001 | | 6/7/2001 | | FAIL |
Bill Alexander
|
|
|
Failed: Still lack required information requested in the review notes.
|
Telephone call | | | 6/7/2001 | | DONE |
|
|
|
Faxed letter of continuing problem and asked for FPE review on next submittal.
|
Sprinkler Plan Check | 5/16/2001 | | 5/25/2001 | | FAIL |
Bill Alexander
|
|
|
Failed: Area 1, Remote 7 and Area 2 remote 2 need calculation reverification for inrack (mezzanine) pressures. Inrack heads (mezzanine) require staggering in the Transvewrse flue space. Verification of elevation for Area 1 Remote 7. All other items/areas seem acceptable to proceed.
|
Meeting | | | 5/18/2001 | | DONE |
|
|
|
Had a meeting with Fennerran to go through problems.
|
INSP-Sprinkler Rough-in | 3/5/2001 | 3/6/2001 | 3/6/2001 | A | FAIL |
Rick Jackson
|
|
|
stub in\\###-#### underground permit not approved; this permit is for the overhead 3/6/2001 3:11:48 PM
|
Plan assigned to (Bill) | 1/25/2001 | | 3/6/2001 | | DONE |
|
|
|
3/6/2001 09:37:41 JWA - activity updated through activity FIRA22 from case FIR01-00096.
|
Telephone call | | | 2/13/2001 | | DONE |
Bill Alexander
|
|
|
Faxed copy of failed review and asked for a conference.
|
Sprinkler Plan Check | 1/25/2001 | | 2/13/2001 | | FAIL |
Bill Alexander
|
|
|
Lack correct design approches of NFPA 13 and related.
|
Application received | | | 1/25/2001 | | PASS |
Bill Alexander
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|