DOC - Permit Finaled | 5/9/2001 | 5/9/2001 | 5/9/2001 | P | PASS |
Joe Tawney
|
|
|
Finaled by inspector at 5/9/2001 3:17:06 PM
|
INSP-Final Inspection | 3/23/2001 | 3/23/2001 | 3/23/2001 | P | PART |
Joe Tawney
|
|
|
OK on underground and above ground hydro tests and partial spklr rough in 3/26/2001 8:26:54 AM
|
INSP-Supply line flush | 3/22/2001 | 3/22/2001 | 3/22/2001 | P | PART |
Joe Tawney
|
|
|
OK on supply line flush 3/23/2001 8:20:30 AM
|
Issue permit | | | 3/19/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | 3/16/2001 | | 3/16/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2001 | | PASS |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 3/14/2001 | | 3/15/2001 | | PASS |
Bill Alexander
|
|
|
|
Telephone call | | | 3/9/2001 | | DONE |
|
|
|
talked to commerial fire pro to verify plans are ready-no fees-failed per bill
|
Issue permit | | | 3/9/2001 | | DONE |
|
|
|
plans failed, gave them back
|
Plan assigned to (Bill) | 2/26/2001 | | 3/9/2001 | | DONE |
|
|
|
3/9/2001 09:20:48 JWA - activity updated through activity FIRA22 from case FIR01-00081.
|
Sprinkler Plan Check | 2/27/2001 | | 3/9/2001 | | FAIL |
Bill Alexander
|
|
|
Does not meet calculation design approach requirements of NFPA 13 Chapter 8.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2001 | | FAIL |
Bill Alexander
|
|
|
|
Application received | | | 2/26/2001 | | PASS |
Bill Alexander
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|