DOC - Permit Finaled | 12/5/2001 | 12/5/2001 | 12/5/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/5/2001 5:01:06 PM Fire sprinkler system finaled
|
INSP-Supply line flush | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PASS |
Joe Tawney
|
|
|
OK on underground hydro test 8/20/2001 12:07:01 PM
|
INSP-Final Inspection | 8/16/2001 | 8/17/2001 | 8/17/2001 | A | FAIL |
Joe Tawney
|
|
|
Final Fail need UG hydro test and Spklr head in riser room 8/17/2001 2:16:56 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2001 | 7/16/2001 | 7/16/2001 | P | PART |
Joe Tawney
|
|
|
Ok on above ground hydro test and supply line flush 7/16/2001 3:14:28 PM
|
INSP-Supply line flush | 7/12/2001 | 7/13/2001 | 7/13/2001 | P | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 13:59:18. Contact: ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 7/12/2001 | 7/13/2001 | 7/13/2001 | P | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 13:59:51. Contact: ###-####.
|
INSP-Supply line flush | 7/2/2001 | 7/3/2001 | 7/3/2001 | A | CANC |
Joe Tawney
|
|
|
Cancel Leak in line 7/3/2001 10:54:23 AM
|
INSP-Sprinkler Rough-in | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Joe Tawney
|
|
|
###-#### Spklr rough in OK to cover 5/30/2001 9:31:08 AM
|
Issue and Print Permit | | | 4/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | 3/14/2001 | | 3/14/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/14/2001 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (Bill) | 3/7/2001 | | 3/13/2001 | | DONE |
|
|
|
3/13/2001 16:40:12 JWA - activity updated through activity FIRA22 from case FIR01-00099.
|
Sprinkler Plan Check | 3/8/2001 | | 3/13/2001 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2001 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 3/7/2001 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|