INSP-Final Inspection | 12/28/2001 | 12/28/2001 | 12/28/2001 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/28/2001 8:36:17 AM System finaled
|
DOC - Permit Finaled | 12/28/2001 | 12/28/2001 | 12/28/2001 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 12/28/2001 8:36:26 AM
|
Issue and Print Permit | | | 7/3/2001 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/2/2001 | | 7/2/2001 | | DONE |
Bill Alexander
|
|
|
Piping changes and calc reverifications
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2001 | | DONE |
Bill Alexander
|
|
|
|
Telephone call | | | 7/2/2001 | | DONE |
|
|
|
left mess that permit is ready
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2001 | 6/27/2001 | 6/27/2001 | P | PART |
Joe Tawney
|
|
|
OK on underground and above hydro tests. Spklr rough in Spklr overspaced in large rooms with upright spklrs. Exposed wood and may need coverage under stairs near atrium 6/27/2001 3:55:35 PM
|
INSP-Supply line flush | 6/13/2001 | 6/13/2001 | 6/13/2001 | P | PART |
Joe Tawney
|
|
|
Israel ###-#### OK on supply line flush 6/13/2001 1:36:26 PM
|
INSP-Sprinkler Rough-in | 5/29/2001 | 5/30/2001 | 5/30/2001 | P | PART |
Joe Tawney
|
|
|
OK to cover hard lid area on 2nd floor West side 5/30/2001 1:22:32 PM
|
INSP-Sprinkler Rough-in | 5/18/2001 | 5/21/2001 | 5/21/2001 | P | PART |
Joe Tawney
|
|
|
OK to cover spklr supply line 5/21/2001 1:39:31 PM
|
Inspection Record Card- Fire | 3/28/2001 | | 3/28/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/28/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Issue permit | | | 3/28/2001 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 3/15/2001 | | 3/27/2001 | | DONE |
|
|
|
3/27/2001 20:08:04 SLR - activity updated through activity FIRA22 from case FIR01-00125.
|
Sprinkler Plan Check | | | 3/27/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2001 | | PASS |
|
|
|
|
Application received | | | 3/15/2001 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|