INSP-Final Inspection | 12/5/2003 | 12/8/2003 | 12/8/2003 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/5/2003 at 4:30:50 PM. Contact: ###-####.
|
DOC - Permit Finaled | 12/8/2003 | 12/8/2003 | 12/8/2003 | A | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 12/8/2003 8:17:44 AM
|
INSP-Final Inspection | 10/27/2003 | 10/29/2003 | 10/29/2003 | P | PASS |
Rick Jackson
|
|
|
all deficencies remedied. Please call 1 hour prior to arrival; Phone #: ###-#### Internet Inspection Request from: Trent Bice will close out sthis permit when alarms (FIR01-00152) is completed; still need test certificates 10/29/2003 3:40:00 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2003 | 8/15/2003 | 8/15/2003 | A | FAIL |
Rick Jackson
|
|
|
Trip tests, and alarm test on the fire sprinkler system. Please call in the A.M. so we can have things ready when you arrive.; Phone #: ###-#### Internet Inspection Request from: Trent Bice need head under overhead door and return bends; remove main; need sign on door - Fire Sprinkler Controls - Fire Alarm Panel; keep hose valves clear of storage; obtain approval for 62 second trip time; provide locks on EOL acclerator; lock on PIV; PIV tamper undergorund conduit not listed for underground service; 8/15/2003 11:48:10 AM
|
(F) Reprint permit | | | 7/29/2003 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/29/2003 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/22/2003 | | 7/28/2003 | | PASS |
Bill Alexander
|
|
|
Revised system #2 piping to drop volume for required trip time test.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2003 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 7/28/2003 | | 7/28/2003 | | DONE |
|
|
|
|
Telephone call | | | 7/28/2003 | | DONE |
|
|
|
permit ready and fees due
|
Plan resubmittals received | | | 7/22/2003 | | |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 6/3/2003 | | DONE |
Bill Alexander
|
|
|
Sent email to S. Fenneren to get this project going and finished.
|
Telephone call | | | 5/13/2003 | | DONE |
Bill Alexander
|
|
|
Contractor called and said the (new) FM approved DPV was shipped from Israel. Questioned me if their hold up on sprinklers would hold up a BLD. My answer was "no", not if they show continuing work to get it finaled.
|
INSP-Conference | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | DONE |
Rick Jackson
|
|
|
Talked to Trent (Shilo) and told him he has 30 days to complete the work; he said they have delays in communication with the maker of the new valve; he is due back in town next Wednesday and will provide info on the valve to Bill Alexander; I asked about the trip times and he said that at 21 psi it takes 1:08 and at 17 psi it takes 57 seconds
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2002 | 4/29/2002 | 4/29/2002 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 04/26/2002 at 16:31:42. Contact: ###-####. reviewed c/n issued - some items corrected; storage height of records too high; need to verify EQ's in west warehouse; 4/29/2002 4:49:39 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2001 | 11/2/2001 | 11/2/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/02/2001 at 08:21:12. Contact: ###-####. c/n issued; too long to list 11/2/2001 4:24:47 PM
|
Issue permit | | | 11/1/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/31/2001 | | DONE |
|
|
|
permit ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2001 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 10/25/2001 | | 10/31/2001 | | PASS |
Bill Alexander
|
|
|
Requires fire hose resubmittal meeting requirements of NFPA 13:5-15.5, and UFC 8102.9.
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2001 | 10/24/2001 | 10/24/2001 | A | NR |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 10/23/2001 4:39:21 PM need plans at job; told Trent that I need the plans before inspection 10/25/2001 7:23:28 AM
|
INSP-Sprinkler Rough-in/Hydro | 10/22/2001 | 10/23/2001 | 10/23/2001 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/22/2001 at 09:37:56. Contact: ###-####.
|
Sprinkler Plan Check | 7/17/2001 | | 7/19/2001 | | FAIL |
Bill Alexander
|
|
|
Resubmittal on Firematic Exhauster - to meet NFPA 13:4-2.3.1 (volume limitations) . Does not meet listing requirements of manufacturers use and application, required per NFPA 13:3-1.1.
|
INSP-Supply line flush | 6/1/2001 | 6/4/2001 | 6/4/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/01/2001 at 13:29:05. Contact: ###-####. underground flush okay 6/4/2001 2:07:00 PM
|
INSP-Supply line flush | 5/31/2001 | 6/1/2001 | 6/1/2001 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/31/2001 at 15:00:26. Contact: ###-####. United Water will turn on valve on Monday 6/4/01 6/1/2001 10:23:05 AM
|
INSP-Supply line flush | 5/24/2001 | 5/24/2001 | 5/24/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/24/2001 at 08:27:21. Contact: ###-####. underground installed is 8 inch per plans but PIV not installed. Shilo notified per telephone call to Pepper 5/24/2001 11:37:29 AM
|
Issue and Print Permit | | | 4/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/4/2001 | | 4/4/2001 | | DONE |
|
|
|
|
Telephone call | | | 4/4/2001 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Plan assigned to (Bill) | 3/15/2001 | | 4/2/2001 | | DONE |
|
|
|
4/2/2001 14:04:15 SLR - activity updated through activity FIRA22 from case FIR01-00126.
|
Sprinkler Plan Check | 3/28/2001 | | 4/2/2001 | | PASS |
|
|
|
Re-submittal. Consider only as 2 submittals. Revisions made by RLD
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2001 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/15/2001 | | 3/19/2001 | | FAIL |
Bill Alexander
|
|
|
LACK NFPA MINIMUM REQUIREMENTS.
|
Telephone call | | | 3/19/2001 | | DONE |
Bill Alexander
|
|
|
FAXED COPY OF FAILED REVIEW NOTES
|
Application received | | | 3/15/2001 | | PASS |
Bill Alexander
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|