DOC - Permit Finaled | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 12/17/2001 10:31:55 AM
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 07/02/2001 at 11:26:11. Contact: ###-####.-- -wrong permit #
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PART |
Joe Tawney
|
|
|
Spklr rough in Finish EQ bracing of risers, Add 1 head is storage area, Address beam obstruction in storage area 7/2/2001 4:53:44 PM
|
INSP-Supply line flush | 6/8/2001 | 6/8/2001 | 6/8/2001 | P | PART |
Joe Tawney
|
|
|
OK on supply line flush 6/8/2001 1:39:32 PM
|
INSP-Supply line flush | 6/6/2001 | 6/7/2001 | 6/7/2001 | P | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/06/2001 at 08:17:46. Contact: ###-####.----cancel per shilo
|
INSP-Supply line flush | 6/6/2001 | 6/7/2001 | 6/7/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel water not turned yet 6/7/2001 2:10:43 PM
|
INSP-Supply line flush | 4/25/2001 | 4/25/2001 | 4/25/2001 | P | PASS |
Joe Tawney
|
|
|
4/26/2001 8:56:24 AM OK to cover spklr supply line 4/26/2001 8:56:42 AM
|
INSP-Supply line flush | 4/23/2001 | 4/23/2001 | 4/23/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel To be rescheduled 4/23/2001 1:29:17 PM
|
INSP-Supply line flush | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/19/2001 at 14:55:55. Contact: ###-####. OK on supply line stub in to bldg 4/20/2001 11:55:20 AM
|
Inspection Record Card- Fire | 4/4/2001 | | 4/4/2001 | | DONE |
|
|
|
|
Telephone call | | | 4/4/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Issue permit | | | 4/4/2001 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 3/28/2001 | | 4/3/2001 | | DONE |
|
|
|
4/3/2001 20:52:15 SLR - activity updated through activity FIRA22 from case FIR01-00149.
|
Sprinkler Plan Check | 4/3/2001 | | 4/3/2001 | | PASS |
|
|
|
RUSHED PROJECT AT CONTRACTOR'S REQUEST. RESUBMITTAL APPROVED WITH CONDITIONS.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2001 | | PASS |
|
|
|
|
Sprinkler Plan Check | 3/30/2001 | | 3/31/2001 | | FAIL |
|
|
|
RUSH REQUEST. Faxed review comments to sprinkler Contractor.
|
Application received | | | 3/28/2001 | | |
|
|
|
|