INSP-Sprinkler Rough-in/Hydro | 2/13/2002 | 2/15/2002 | 2/15/2002 | A | CANC |
Troy Cobbley
|
|
|
duplicate inspection 2/15/2002 2:04:38 PM
|
INSP-Final Inspection | 2/15/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 2/15/2002 2:00:58 PM Fire sprinkler system finaled. Underground and overhead hydro tests OK
|
DOC - Permit Finaled | 2/15/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 2/15/2002 2:01:04 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2001 | 11/29/2001 | 11/29/2001 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in OK. 11/29/2001 2:58:50 PM
|
INSP-Supply line flush | 9/5/2001 | 9/6/2001 | 9/6/2001 | A | PART |
Joe Tawney
|
|
|
OK on supply line flush 9/6/2001 11:55:12 AM
|
INSP-Supply line flush | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | PART |
Joe Tawney
|
|
|
OK to cover supply line 6/5/2001 11:23:10 AM
|
INSP-Supply line flush | 5/30/2001 | 5/31/2001 | 5/31/2001 | P | PART |
Joe Tawney
|
|
|
OK to cover under slab main 5/31/2001 1:50:58 PM Ok to cover stub in supply line to bldg 5/31/2001 1:54:10 PM
|
Telephone call | | | 4/13/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Issue permit | | | 4/13/2001 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 4/9/2001 | | 4/12/2001 | | DONE |
|
|
|
4/12/2001 09:45:53 SLR - activity updated through activity FIRA22 from case FIR01-00198.
|
Sprinkler Plan Check | | | 4/12/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2001 | | PASS |
|
|
|
|
Inspection Record Card- Fire | 4/12/2001 | | 4/12/2001 | | DONE |
|
|
|
|
Application received | | | 4/9/2001 | | |
|
|
|
|