INSP-Final Inspection | 12/13/2001 | 12/13/2001 | 12/13/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/13/2001 4:38:15 PM
|
DOC - Permit Finaled | 12/13/2001 | 12/13/2001 | 12/13/2001 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 12/13/2001 4:38:21 PM
|
INSP-Final Inspection | 7/25/2001 | 7/25/2001 | 7/25/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 7/25/2001 8:44:12 AM bsck flow preventer cycling 7/25/2001 10:26:16 AM
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2001 | 7/24/2001 | 7/24/2001 | P | PASS |
Rick Jackson
|
|
|
sam ###-#### underground and overhead hydro test okay 7/24/2001 10:41:26 AM
|
INSP-Supply line flush | 7/11/2001 | 7/11/2001 | 7/11/2001 | P | PASS |
Rick Jackson
|
|
|
###-#### underground flush okay; need hydro on underground and FDC 7/11/2001 2:12:45 PM
|
INSP-Sprinkler Rough-in | 6/20/2001 | 6/20/2001 | 6/20/2001 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/20/2001 2:55:55 PM FDC complete to street
|
INSP-Sprinkler Rough-in | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 6/19/2001 1:19:31 PM partial cover for underground
|
INSP-Sprinkler Rough-in | 6/12/2001 | 6/12/2001 | 6/12/2001 | P | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/12/2001 3:28:30 PM combustibles in concealed spaces; hangers; earthquaking; spacing of heads in small attic on south side 6/12/2001 3:30:02 PM
|
Issue permit | | | 5/11/2001 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/9/2001 | | 5/9/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (Bill) | 5/2/2001 | | 5/9/2001 | | DONE |
|
|
|
5/9/2001 14:03:31 JWA - activity updated through activity FIRA22 from case FIR01-00305.
|
Sprinkler Plan Check | 5/4/2001 | | 5/9/2001 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2001 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 5/2/2001 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|