Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberFIR01-00340
StatusFinaled
Name C&S FIRE PROTECTION INC
Site Address 601 N PHILLIPPI ST
Project NameSPR STEIN DISTRIBUTING #1
Customer Number 
ePlanReview 
Description
*STEIN DISTRIBUTING - PHASE ONE* To install fire sprinkler protection which includes the 6" underground supply, 6" riser, and extend protection piping and appurtenance into the 4,883 ft/2 area within the interior of the existing warehouse of cooled space per plans on file. Existing building area noted by architect (Charles Filanowicz) as 50,177 ft/2. This building did NOT have fire sprinkler protection to meet UBC, UFC requirements. OWNER HAS AGREED TO ADD FIRE SPRINKLERS TO THE BUILDING WITHIN A FIVE YEAR PLAN IN ORDER TO MEET FIRE DEPARTMENT REQUIREMENT FOR HIGH PILED STORAGE. THIS AGREEMENT IS ON FILE AND SIGNED BY THE OWNER AND DAVE MILLER. This permit is not attached to a building permit, but would be related to BLD00-03671. *JWA*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  7/31/2001 PASS
DetailsJoe Tawney
Finaled for Joe Tawney per response (email) 07/31/01.
INSP-Sprinkler Rough-in/Hydro7/25/20017/26/20017/26/2001APASS
DetailsJoe Tawney
OK on spklr rough in and OK on above ground hydro test 7/26/2001 2:40:30 PM
INSP-Final Inspection7/25/20017/26/20017/26/2001APASS
DetailsJoe Tawney
Final Pass OK for certificate of completion 7/26/2001 2:39:52 PM
INSP-Supply line flush7/25/20017/26/20017/25/2001ACANC
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/25/2001 at 14:53:50. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 07/25/2001 at 14:54:43.
INSP-Sprinkler Rough-in/Hydro7/24/20017/25/20017/25/2001APART
DetailsJoe Tawney
OK on spklr rough in add earthquake bracing and change two hangers 7/25/2001 2:17:08 PM
INSP-Final Inspection7/24/20017/25/20017/25/2001PNR
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/24/2001 at 13:59:18. Contact: ###-####.
INSP-Supply line flush7/20/20017/23/20017/23/2001APASS
DetailsJoe Tawney
OK on supply line hydro test 7/23/2001 5:30:07 PM
INSP-Sprinkler Rough-in/Hydro7/20/20017/20/20017/20/2001PNR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/20/2001 at 10:06:20. Contact: ###-####. will reschedule for 7/23 7/20/2001 3:57:42 PM
INSP-Sprinkler Rough-in/Hydro7/18/20017/19/20017/19/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/18/2001 at 15:17:40. Contact: ###-####. underground hydro failed. leak at riser. 7/19/2001 11:11:28 AM
INSP-Supply line flush7/17/20017/17/20017/17/2001PPART
DetailsJoe Tawney
OK on supply line flush 7/17/2001 10:36:47 AM
INSP-Supply line flush7/16/20017/16/20017/16/2001PCANC
DetailsJoe Tawney
Cancel Water not turned on 7/16/2001 1:27:30 PM
INSP-Supply line flush7/10/20017/10/20017/10/2001PPART
DetailsJoe Tawney
OK to cover spklr supply line 7/10/2001 1:33:44 PM
Issue and Print Permit  6/19/2001 DONE
Inspection Record Card- Fire6/15/2001 6/15/2001 DONE
Telephone call  6/15/2001 DONE
Plan assigned to (Bill)5/29/2001 6/15/2001 DONE
6/15/2001 08:08:05 JWA - activity updated through activity FIRA22 from case FIR01-00340.
Sprinkler Plan Check6/6/2001 6/15/2001 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  6/15/2001 DONE
DetailsBill Alexander
Sprinkler Plan Check5/29/2001 6/4/2001 FAIL
DetailsBill Alexander
Calc error, using the wrong temp heads, no info on riser room, no info shown of FDC access, data lacking on BFP, compressor, DPV, air maintenance device, need EQ loads, riser incomplete in detail, etc.
Application received  5/29/2001 PASS
DetailsBill Alexander
Case Summary    DONE