Description
(JOE'S ALL AMERICAN GRILL - BASEMENT) Fire sprinklers are used to substitute for 1-hr fire-resistive construction of the building. To add fire sprinklers in the basement area (5,500 square feet) of an existing system, for an assembly occupancy. Work is to include installation of mains, lines and fire sprinklers throughout, per approved drawings, engineering, and plan review conditions on file. The basement shall be fully fire sprinklered per NFPA 13-1999, as regulated by the Fire Department. This permit is attached to BLD01-01349. *JWA*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Sprinkler Plan Check10/11/2001 10/16/2001 PASS
DetailsBill Alexander
Calculations provided, verifying backflow pressure loss and existing system operation. No plans updated. Rick Jackson signed permit off prior to completion of requirements).
DOC - Permit Finaled8/3/20018/3/20018/3/2001APASS
DetailsRick Jackson
Finaled by inspector at 8/3/2001 9:35:07 AM
INSP-Final Inspection8/3/20018/3/20018/3/2001APASS
DetailsRick Jackson
Added by Inspector: 409 On 8/3/2001 9:35:02 AM
INSP-Final Inspection8/1/20018/1/20018/1/2001PPASS
DetailsRick Jackson
Added by Inspector: 409 On 8/1/2001 1:34:58 PM
DOC - Permit Finaled8/1/20018/1/20018/1/2001PPASS
DetailsRick Jackson
Finaled by inspector at 8/1/2001 1:36:36 PM
INSP-Sprinkler Rough-in/Hydro6/28/20016/29/20016/29/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/28/2001 at 15:30:37. Contact: . need resubmittals; head gaurds; stair not protected; c/n issued 6/29/2001 3:11:27 PM
Inspection Record Card- Fire6/20/2001 6/20/2001 DONE
Telephone call  6/20/2001 DONE
left mess that permit is ready
Issue permit  6/20/2001 DONE
Sprinkler Plan Check6/19/2001 6/19/2001 PASS
DetailsBill Alexander
Partial Approval. Received documents of intent and request to start. Requires verification of other floor calculations for backflow preventer. Need basement plan update. Reference plan review notes. (Job signed off by Rick Jackson without corrected plans or calcs 08/03/2001).
PLANS/APPL TAKEN TO FRONT DESK  6/19/2001 DONE
DetailsBill Alexander
Sprinkler Plan Check6/7/2001 6/18/2001 FAIL
DetailsBill Alexander
LACK DETAIL. LACK COVERAGE UNDER THE STAGE. STORAGE APPEAR OVERSPACED. RISER ROOM APPEAR OVERSPACED. TOO MANY QUESTIONS.
Meeting  6/18/2001 DONE
DetailsBill Alexander
HAD MEETING WITH DESIGN MANAGER, R. KNUTSON, (GRINNELL) AND GAVE BACK ONE PLAN MARKED WITH REQUIRED INFORMATION. 3:45PM
Plan assigned to (Bill)6/7/2001 6/15/2001 DONE
6/15/2001 11:51:02 SLR - activity updated through activity FIRA22 from case FIR01-00328.
Application received  6/7/2001 PASS