Permit Information
Permit NumberFIR01-00355
StatusFinaled
Name TREASURE VALLEY FIRE
Site Address 11311 W CHINDEN BLVD
Project NameSPR HP #6 - 1ST FLR/BSMNT
Customer Number 
ePlanReview 
Description
(H-P BLDG #6) (NICKEL CLEAN ROOM EXPANSION) To modify and expand an existing fire sprinkler system into a fab clean room (H-6) occupancy into previously occupied office space per building permit BLD01-01007 )in which this permit is attached), approved plans on file. Work required is sprinkler modifications for non-combustible framing, 1-hour occupancy separations, two (2) boiler rooms. An extension of 1-hour rated exit corridor 6-127, to the new 1-hour exit passageway on main level. The installation of new exit corridor from basement through south wall. To install, maintain and restore walls, floors and ceiling systems & two hour Area Separation wall between HP Building #6-East & #6-West. To upgrade existing central east - west corridor ceiling system to comply with code. NOTE: This building is fully fire sprinklered. Permit BLD01-00770 issued for demolition & rated corridor extension on main level, of which the sprinkler work under this permit will be involved. Also included is a new underground supply to be located east of the existing supply. The riser will be relocated with this work. All materials, installation shall be per the UFC, NFPA related and adopted pamphlets and BCO, as regulated by the Fire Department. Underground was installed under FIR01-00381. *JWA*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  10/9/2001 PASS
DetailsJoe Tawney
INSP-Final Inspection10/9/200110/9/200110/6/2001 PASS
DetailsJoe Tawney
OK for perm. occ. Sprinklers OK
INSP-Sprinkler Rough-in/Hydro9/26/20019/27/20019/27/2001APART
DetailsJoe Tawney
OK on above and underground hydro tests. OK on sprinkler rough-in. Will advise on corr. obstr. and spklrs in filter banks and pass through. 9/27/2001 12:03:11 PM
INSP-Sprinkler Rough-in/Hydro8/21/20018/22/20018/22/2001APART
DetailsJoe Tawney
spklr rough in Will verify spacing in clean room when ceiling is installed. Basement heads will be inspected when installed under all obstructions. Horizontal obstruction along wall needs to be addressed in corridors. 8/22/2001 11:19:25 AM
Issue permit  7/6/2001 DONE
Inspection Record Card- Fire7/5/2001 7/5/2001 DONE
Telephone call  7/5/2001 DONE
called Jeff Anderson ###-####
Sprinkler Plan Check6/25/2001 7/3/2001 PASS
DetailsJon Williams
PLANS/APPL TAKEN TO FRONT DESK  7/3/2001 DONE
DetailsBill Alexander
Plan assigned to (Bill)6/12/2001 6/27/2001 DONE
6/27/2001 13:41:39 JWA - activity updated through activity FIRA22 from case FIR01-00381.
Sprinkler Plan Check6/13/2001 6/21/2001 FAIL
DetailsBill Alexander
LACK DETAIL OF EXTENT OF WORK. UNDERGROUND UNREADABLE, NODES, PIPE LENGTHS, SIZES MISSING, ETC.
Telephone call  6/21/2001 DONE
FAXED COPY OF FAILED REVIEW TO TREASURE VALLEY 11:00 AM, @ ###-####
Application received  6/12/2001  
Case Summary    DONE