INSP-Final Inspection | 11/7/2001 | 11/7/2001 | 11/7/2001 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler system finaled. OK for perm occ. 11/7/2001 1:01:17 PM
|
DOC - Permit Finaled | 11/7/2001 | 11/7/2001 | 11/7/2001 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 11/7/2001 1:01:29 PM
|
INSP-Final Inspection | 10/22/2001 | 10/23/2001 | 10/23/2001 | A | NR |
Troy Cobbley
|
|
|
Fire alarm system not active. Inspection to be rescheduled. 10/24/2001 8:21:29 AM
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2001 | 9/28/2001 | 9/28/2001 | A | PART |
Joe Tawney
|
|
|
hydo's OK. duct & beam blockage to be fixed in crawlspace 9/28/2001 4:59:15 PM
|
INSP-Final Inspection | 9/27/2001 | 9/28/2001 | 9/27/2001 | P | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 09/27/2001 at 11:17:46. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/27/2001 at 11:21:02.
|
INSP-Supply line flush | 9/6/2001 | 9/7/2001 | 9/7/2001 | A | PART |
Joe Tawney
|
|
|
Ok on supply line and FDC flush 9/7/2001 12:16:30 PM
|
INSP-Supply line flush | 8/30/2001 | 8/31/2001 | 8/31/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/30/2001 at 16:56:13. Contact: ###-####. FDC okay to cover; will to ball drip in crawl space 8/31/2001 2:15:52 PM
|
INSP-Supply line flush | 8/28/2001 | 8/29/2001 | 8/29/2001 | A | PART |
Joe Tawney
|
|
|
OK to cover supply line. Still need to pour thrust block at riser 8/29/2001 10:21:28 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Joe Tawney
|
|
|
Ok on rough in of mostof 1st flr. Provide protection under combustable canopy at front entrance 8/23/2001 4:46:50 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2001 | 8/3/2001 | 8/3/2001 | P | PART |
Joe Tawney
|
|
|
OK on hydro test of audio room behind stage. One head will not cover upstairs area behind stage 8/3/2001 2:44:08 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2001 | 8/3/2001 | 8/3/2001 | P | PART |
Joe Tawney
|
|
|
OK hydro test of audio room behind stage. Need two heads in second level of audio area 8/6/2001 7:55:59 AM
|
INSP-Sprinkler Rough-in/Hydro | 7/20/2001 | 7/23/2001 | 7/23/2001 | P | PART |
Joe Tawney
|
|
|
OK above ground hydro test for West half of sanctuary 7/23/2001 5:23:32 PM
|
INSP-Final Inspection | 7/18/2001 | 7/19/2001 | 7/19/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/18/2001 at 15:19:10. Contact: ###-####. not a final but a hydro inspection of the west side. Fitting broke and hydro failed
|
INSP-Sprinkler Rough-in/Hydro | 7/16/2001 | 7/17/2001 | 7/17/2001 | A | PART |
Joe Tawney
|
|
|
Ok on above ground hydro test for East half of sanctuary 7/17/2001 5:00:50 PM
|
Issue and Print Permit | | | 7/16/2001 | | |
|
|
|
|
Plan assigned to (Bill) | 6/26/2001 | | 7/13/2001 | | DONE |
|
|
|
7/13/2001 10:06:56 JWA - activity updated through activity FIRA22 from case FIR01-00387.
|
Sprinkler Plan Check | 7/11/2001 | | 7/13/2001 | | PASS |
Bill Alexander
|
|
|
REQUIRES RESUBMITTAL OF PENDING ISSUES PRIOR TO FIELD ACCEPATANCE.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2001 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 7/13/2001 | | 7/13/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/13/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Telephone call | | | 7/6/2001 | | DONE |
|
|
|
Faxed copy of failed review and updated cover sheets. Took failed plans to desk to call for return or destroy in a week.
|
Telephone call | | | 7/6/2001 | | DONE |
|
|
|
called ###-#### left a message with Clarence to pick up failed plans. They will be thrown away in one week...
|
Sprinkler Plan Check | 6/26/2001 | | 7/6/2001 | | FAIL |
Bill Alexander
|
|
|
Lack correct piping, remote area question, lack UG detail, etc.
|
Application received | | | 7/5/2001 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|