INSP-Sprinkler Rough-in/Hydro | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | PASS |
Rick Jackson
|
|
|
TRENT ###-####
|
DOC - Permit Finaled | 6/12/2002 | 6/12/2002 | 6/12/2002 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 6/12/2002 1:15:44 PM
|
INSP-Final Inspection | 6/12/2002 | 6/12/2002 | 6/12/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/12/2002 1:16:28 PM
|
INSP-Supply line flush | 3/11/2002 | 3/12/2002 | 3/12/2002 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/11/2002 at 12:25:12. Contact: ###-####. flow still very low 3/12/2002 4:26:52 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2002 | 1/29/2002 | 1/29/2002 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 01/29/2002 at 09:28:00. Contact: ###-####. okay ro cover - r/i okay; still need hydro; underground will need flush and hydro 1/29/2002 3:01:56 PM
|
INSP-Supply line flush | 1/11/2002 | 1/14/2002 | 1/15/2002 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 1/11/2002 2:15:53 PM received a call from Dan with Shilo. He said the other underground supplies were flushed and they produced a lot more water than this one and they will proceed with other trouble shooting to determine why this flush is so low on flow 1/15/2002 11:50:37 AM
|
INSP-Supply line flush | 1/10/2002 | 1/11/2002 | 1/11/2002 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 01/10/2002 at 14:02:42. Contact: ###-####. very limited flow on underground flush. shilo to retest other buildings up stream from this building on monday 1/14 1/11/2002 2:15:30 PM
|
Issue permit | | | 11/9/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2001 | | DONE |
|
|
|
talked to bob to verify plans are ready
|
Sprinkler Plan Check | 10/12/2001 | | 10/18/2001 | | PASS |
Bill Alexander
|
|
|
2nd CHANGE - Garage protection requirements NFPA 13R:2-6.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2001 | | DONE |
Bill Alexander
|
|
|
|
INSP-Sprinkler Rough-in | 10/10/2001 | 10/10/2001 | 10/10/2001 | P | PART |
Rick Jackson
|
|
|
###-#### underground flush only - pass 10/10/2001 3:15:35 PM
|
INSP-Sprinkler Rough-in | 10/8/2001 | 10/8/2001 | 10/8/2001 | P | NR |
Rick Jackson
|
|
|
mike ###-#### underground
|
Inspection Record Card- Fire | 9/14/2001 | | 9/14/2001 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/31/2001 | | 9/13/2001 | | PASS |
Bill Alexander
|
|
|
Garage protection requirements NFPA 13R:2-6, and add protection in in two interior stairs.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2001 | | DONE |
Bill Alexander
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 8/17/2001 | 8/17/2001 | 8/17/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 08:16:36. Contact: ###-####. underground okay to cover 8/17/2001 1:10:23 PM
|
Inspection Record Card- Fire | 8/10/2001 | | 8/10/2001 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/10/2001 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 8/6/2001 | | 8/9/2001 | | DONE |
|
|
|
8/9/2001 16:46:44 JWA - activity updated through activity FIRA22 from case FIR01-00427.
|
Sprinkler Plan Check | 8/6/2001 | | 8/9/2001 | | PART |
Bill Alexander
|
|
|
Exception provided-requires protection in the garages and 2 stairs and approved control valves and tamper devices.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/9/2001 | | PART |
Bill Alexander
|
|
|
|
Application received | | | 8/6/2001 | | PASS |
Bill Alexander
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|