INSP-Final Inspection | 2/23/2005 | 2/24/2005 | 2/24/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled 2/24/2005 9:29:08 AM
|
DOC - Permit Finaled | 2/24/2005 | 2/24/2005 | 2/24/2005 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 2/24/2005 9:29:13 AM
|
CHANGE STATUS TO (ISS) | | | 9/22/2004 | | DONE |
|
|
|
Re-issued
|
(F) Reprint permit | | | 9/22/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 9/20/2004 | | PASS |
|
|
|
Plan Modification (As-builts) of entire fire alarm system to this date. Resubmittal was required as part of the finalization of this FIR. See entry dated 9/15/2004 per Rick Jackson's requirements.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/20/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/20/2004 | | 9/20/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/20/2004 | | DONE |
|
|
|
Spoke with Chris and told him that permit is ready & fees///9/20/04 2:35pm BAS
|
Plan resubmittals received | | | 9/17/2004 | | |
|
|
|
|
INSP-Final Inspection | 9/14/2004 | 9/15/2004 | 9/15/2004 | A | FAIL |
Rick Jackson
|
|
|
bryan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Need updated, rated door on shaft and resubmittals 9/15/2004 10:08:10 AM
|
INSP-Final Inspection | 8/20/2004 | 8/23/2004 | 8/23/2004 | P | FAIL |
Rick Jackson
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Need plan modifications due to deletions/additions; need rated doors at access holes in top of shaft to maintain 2 hr shaft; need mechanical engineering analysis for Gino's TI and plans to match changes 8/23/2004 4:21:32 PM
|
INSP-Final Inspection | 8/18/2004 | 8/19/2004 | 8/19/2004 | P | PART |
Troy Cobbley
|
|
|
BRAIN; Phone #: ###-#### Internet Inspection Request from: Annette Moore
Completed elevator testing on North and South elevators; acceptable per the drawings.
Completed sprinkler testing on fire pump, Dry System A and Dry System B; acceptable per the drawings.
Left to test:
All existing kitchen hoods (less Gino's Pizzeria and Creapery).
Center elevator, controls being installed on Friday 8/20/2004.
HVAC shutdown system for Gino's Pizzeria.
|
INSP-Final Inspection | 8/10/2004 | 8/13/2004 | 8/13/2004 | P | FAIL |
Rick Jackson
|
|
|
BRIAN; Phone #: ###-#### Internet Inspection Request from: Annette Moore See notes from Mary F. 8/13/2004 4:37:42 PM
|
Miscellaneous action | | | 8/13/2004 | | DONE |
|
|
|
Field tested the following (acceptable):
2 - antifreeze valve tampers
2 - dry system valve tampers (A&B)
6 - fire pump valve tampers
1 - fire pump run
Need to retest the following:
1 - fire pump flow switch
2 - dry system HI/LO pressure (A&B)
2 - dry system flows (A&B)
Items not tested:
Cooking hood monitoring points for Gino's (existing), Shige, Piper Pub, Crapery and Pita Pit.
Failure on the field test:
Elevators: plans show primary and alternate recall, there was nothing connected to the elevator controls for any recall, Romar trying to get the elevator company out on Monday.
Gino's: Duct detector installed in the supply side of the MAU, return air plenum above ceiling with 3 heat pumps, supply air mixing in plenum, needs to be reviewed by the designer.
Gino's cooking hood (existing): Stopped the inspection at this point, the hood appeared exceptionally greasy and I could not find any cleaning or inspection stickers.
|
INSP-Conference | 7/13/2004 | 7/13/2004 | 7/13/2004 | P | PART |
Rick Jackson
|
|
|
brian - note:capital terrace parking garage; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Met with Brian and smoke detectors are required at top of the shaft in each beam pocket 7/13/2004 4:04:27 PM
|
INSP-Conference | 4/5/2004 | 4/6/2004 | 4/6/2004 | A | PART |
Rick Jackson
|
|
|
robert; Phone #: ###-#### Internet Inspection Request from: Darla Downs Met with Robert about the scope of this permit; Larry H. has approved the addition of the hood systems to the alarm panel and the connection of the alarm panels but has not approved any other work; I need a conference with Sam and Mary about the scope of work of this permit 4/6/2004 11:21:39 AM
|
Plan assigned to (SAM) | 8/7/2001 | | 2/27/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 2/27/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/27/2004 | | 2/27/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2004 | | DONE |
|
|
|
|
Telephone call | | | 2/27/2004 | | DONE |
|
|
|
called chris permit ready & fee given 2-27-04 2:24 ///dld
|
Issue and Print Permit | | | 2/27/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/19/2004 | | DONE |
|
|
|
|
Alarm Plan Check | 5/9/2002 | | 5/16/2002 | | FAIL |
|
|
|
Plans do not address all items speicified in previous review and some proposed plan modifications do not meet Code requirements. Revised review comments faxed to Simplex and discussed by phone with Stephanie, Peter and Chris. Also discussed with Larry Hansen.
|
Alarm Plan Check | | | 3/4/2002 | | FAIL |
|
|
|
CONDITIONAL APPROVAL TO BEGIN FIELD INSTALLATION granted prior to receiving REQUIRED resubmittal.
|
Alarm Plan Check | 2/15/2002 | | 3/1/2002 | | PEND |
|
|
|
Plan review of resubmittal not completed due to need for additional information. Per telcon with Stephanie Cribbs, Simplex, information will be provided on Monday.
|
Alarm Plan Check | | | 9/6/2001 | | PEND |
|
|
|
Plans are not comlete and do not include interconnection requirements to the high rise portion. Discussed plan modifications required by phone with Peter Petronich and Teroy Cobbley 9/6, they will resubmit revised plans. This will not be considered a "review" as we are just establishing requirements at this point.
|
Application received | | | 8/7/2001 | | |
|
|
|
|