INSP-Final Inspection | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/17/2001 10:51:54 AM
|
DOC - Permit Finaled | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 12/17/2001 10:52:00 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/17/2001 10:51:34 AM hydro okay
|
INSP-Supply line flush | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PASS |
Rick Jackson
|
|
|
###-#### MIKE
|
INSP-Sprinkler Rough-in | 10/17/2001 | 10/17/2001 | 10/17/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 10/17/2001 3:06:14 PM resubmittal required due to change of fire service main; okay to cover 10/17/2001 3:19:49 PM
|
INSP-Sprinkler Rough-in | 8/13/2001 | 8/13/2001 | 8/13/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 8/13/2001 9:25:52 AM okay to cover 6 inch supply line only; thrust blocks installed and clearance at floor provided by insulation 8/13/2001 10:08:56 AM
|
Issue permit | | | 8/13/2001 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 8/9/2001 | | 8/10/2001 | | DONE |
|
|
|
8/10/2001 13:56:24 JWA - activity updated through activity FIRA22 from case FIR01-00442.
|
Inspection Record Card- Fire | 8/10/2001 | | 8/10/2001 | | DONE |
|
|
|
|
Telephone call | | | 8/10/2001 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Sprinkler Plan Check | 8/10/2001 | | 8/10/2001 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2001 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 8/8/2001 | | 8/9/2001 | | FAIL |
Bill Alexander
|
|
|
PLANS LACK CLARITY FOR ACCEPTANCE. (UFC 1001.3)
|
Application received | | | 8/8/2001 | | DONE |
Bill Alexander
|
|
|
|