TO INSTALL A WET, OH-2 FIRE SPRINKLER SYSTEM, WHICH INCLUDES UNDERGROUND SUPPLY OF 107 FT OF 6" C-900 PVC, INTO A NEW 9,690 FT/2 (THIS INCLUDES A 690 SQ. FT. MEZZANINE), ONE STORY, STEEL, PRE-ENGINEERED EQUIPMENT SALES AND SERVICE BUILDING. THE EXTERIOR OF THE BUILDING IS CONSTRUCTED OF A PRE-ENGINEERED STRUCTURAL STEEL SUPPLIED BY METALLIC BUILDING COMPANY (ICBO REPORT #FA-337). THE SHOP AREA IS CLASSIFIED AS AN H-4 OCCUPANCY AND IS REQUIRED TO BE FIRE SPRINKLERED. ALL INSTALLATION CONSTRUCTION PER THE PLANS AND ATTACHED COMMENT REVIEW NOTES AS REGULATED BY THE FIRE DEPARTMENT. (JWA)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled11/9/200111/9/200111/9/2001APASS
DetailsRick Jackson
Finaled by inspector at 11/9/2001 8:19:00 AM
INSP-Final Inspection11/7/200111/8/200111/9/2001PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 11/07/2001 at 11:41:18. Contact: ###-####.
INSP-Sprinkler Rough-in/Hydro10/29/200110/30/200110/30/2001APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/29/2001 at 13:45:06. Contact: ###-####. hydro on overhead okay 10/30/2001 10:17:22 AM
INSP-Sprinkler Rough-in10/24/200110/25/200110/25/2001PPART
DetailsRick Jackson
###-#### BECKY riser not complete; overhead per plans 10/25/2001 3:22:16 PM
INSP-Sprinkler Rough-in/Hydro10/23/200110/24/200110/23/2001ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/23/2001 at 10:50:49. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/23/2001 at 15:08:06.
INSP-Supply line flush10/22/200110/23/200110/22/2001PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/22/2001 at 16:10:00. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/22/2001 at 16:13:07.
INSP-Sprinkler Rough-in/Hydro10/17/200110/18/200110/18/2001APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/17/2001 at 17:03:37. Contact: ###-####. okay to cover mezz and bathrooms only 10/18/2001 9:26:21 AM
Issue and Print Permit  10/2/2001 DONE
Inspection Record Card- Fire10/1/2001 10/1/2001 DONE
Telephone call  10/1/2001 DONE
Plan assigned to (Bill)9/20/2001 9/28/2001 DONE
9/28/2001 16:39:04 JWA - activity updated through activity FIRA22 from case FIR01-00513.
Sprinkler Plan Check9/21/2001 9/28/2001 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  9/28/2001 DONE
DetailsBill Alexander
Application received  9/20/2001  
Case Summary    DONE