Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR01-00515
StatusFinaled
Name PETRA INC
Site Address 3795 S DEVELOPMENT AVE
Project NameSPR SYRINGA/PMT BUILDING
Customer Number 
ePlanReview 
Description
(SYRINGA / PMT) TO FIRE SPRINKLER A NEW 10,000 FT/2, ONE STORY OFFICE SHELL BUILDING WITH A 110 FT/2, FIRE SPRINKLER RISER/ELECTRICAL ROOM. THIS BUILDING IS CONSTRUCTED OF CONCRETE TILT-UP EXTERIOR WALLS WITH STEEL INTERIOR STRUCTURAL FRAME AND STEEL ROOF JOIST WITH METAL ROOF DECK AND SINGLE PLY ROOFING SYSTEM. THIS BUILDING IS FULLY FIRE SPRINKLERED FOR FUTURE BUILDING AREA INCREASE. THIS PERMIT ALSO INCLUDES RELATED 550 FT/2 RESTROOM CORE, 5,600 FT/2 UTILITY SWITCH GERA AND OFFICE TENANT SPACE. THIS IS RELATED TO NEW NON BEARING WALLS, 2 RESTROOMS, 1HR OCCUPANCY SEPARATION FOR BATTERY ROOM AND SUSPENDED CEILINGS. SYSTEM DESIGN IS OH1 & 2 HAZARD OCCUPANCIES, WITH A WET SYSTEM. DOUBLE INTERLOCKED PRE-ACTION SYSTEM SHALL BE INSTALLED IN THE BATTERY/SWITCHGEAR ROOM. INSTALLATION, EQUIPMENT, CONSTRUCTION SHALL BE PER THE PLANS AND ATTACHED REVIEW LIST, NFPA 13-1999, AS REGULATED BY THE FIRE DEPARTMENT. THIS PERMIT IS ATTACHED TO BLD01-01316. ALSO ASSOCIATED WITH TENANT IMPROVEMENT, BLD01-02151. UNDERGROUND FIRE SERVICE SUPPLY INSTALLED UNDER: FIR01-00442. (JWA)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled1/30/20021/30/20021/30/2002PPASS
DetailsRick Jackson
Finaled by inspector at 1/30/2002 3:25:38 PM
INSP-Final Inspection1/30/20021/30/20021/30/2002PPASS
DetailsRick Jackson
Added by Inspector: 409 On 1/30/2002 3:23:08 PM
INSP-Sprinkler Rough-in/Hydro12/14/200112/17/200112/17/2001APART
DetailsRick Jackson
MIKE ###-#### AND AN UNDER GROUND HYDRO hydro for above ground okay 12/17/2001 10:52:25 AM
INSP-Sprinkler Rough-in/Hydro12/3/200112/3/200112/3/2001PPART
DetailsRick Jackson
mike ###-#### hydro on preaction okay 12/4/2001 4:40:15 PM
INSP-Sprinkler Rough-in/Hydro11/5/200111/5/200111/5/2001PPART
DetailsRick Jackson
###-#### mike FDC hydro okay; partial r/i okay - need heads and drops installed 11/5/2001 3:37:22 PM
INSP-Final Inspection10/17/200110/18/200110/18/2001AFAIL
DetailsRick Jackson
UNDER GROUND ###-#### JIM called in on wrong permit 10/18/2001 9:27:37 AM
Issue permit  10/15/2001 DONE
Sprinkler Plan Check10/8/2001 10/11/2001 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  10/11/2001 DONE
DetailsBill Alexander
Telephone call  10/11/2001 DONE
left mess that permit is ready
Inspection Record Card- Fire10/11/2001 10/11/2001 DONE
Sprinkler Plan Check9/26/2001 10/4/2001 PASS
DetailsBill Alexander
Partial-Approvedl to start with resubmittal and approval on precation system. No work allowed on preaction system.
Telephone call  10/4/2001 DONE
Faxed copy of failed review and condtions.
PLANS/APPL TAKEN TO FRONT DESK  10/4/2001 DONE
DetailsBill Alexander
Partial approval-resubmittal required
Plan assigned to (Bill)9/13/2001 10/4/2001 DONE
10/4/2001 09:41:10 JWA - activity updated through activity FIRA22 from case FIR01-00515.
Inspection Record Card- Fire10/4/2001 10/4/2001 DONE
Telephone call  10/4/2001 DONE
left mess that permit is ready
Issue permit  10/4/2001 DONE
Sprinkler Plan Check9/13/2001 9/24/2001 FAIL
DetailsBill Alexander
Calculations need reverification.
Application received  9/13/2001  
Case Summary    DONE
Case Summary    DONE