Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR01-00522
StatusFinaled
Name TREASURE VALLEY FIRE
Site Address 6140 W CURTISIAN AVE Unit: #200 & #300
Project NameSPR ST AL'S MOB #6, 2 & 3 FLR.
Customer Number 
ePlanReview 
Description
(ST ALPHONSUS MOB #6-IDAHO CARDIOLOGY ASSOCIATES-2ND & 3RD FLOORS) Modify existing system and add sprinklers in a new, 31,172 ft/2, Light Hazard Occupancy tenant, located on entire second and third floors of building shell, permitted under BLD00-01744 for a (UFC - B occupancy) medical office use and (UFC I-1.2 occupancy) ambulatory/outpatient surgery center use. All work per approved plans on file and attached comment list, meeting the UFC and related NFPA pamphlets, as regulated by the Fire Department. Each floor is approximately 15,586 ft/2. Work to include two-hour rated occupancy separation between B and I-1.2 occupancies, new two-hour rated stair shaft for new interior stairway between the 2nd and 3rd floors, fire resistive materials on new steel structural members at new stair opening, new one-hour fire rated exit corridor, one-hour rated medical gas room in basement of building, restrooms and showers, interior walls, access floor system in one room, suspended ceiling installation. This fire permit is attached to building permit: FIR01-01172.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled2/12/20022/12/20022/12/2002PPASS
DetailsTroy Cobbley
Added by Inspector: 430 On 2/12/2002 4:52:24 PM Fire alarm system finaled
DOC - Permit Finaled2/8/20022/8/20022/8/2002PPASS
DetailsTroy Cobbley
Added by Inspector: 430 On 2/8/2002 12:39:14 PM Fire sprinkler system finaled
Sprinkler Plan Check2/7/2002 2/7/2002 PASS
DetailsBill Alexander
3rd floor records storage room sprinkler change to apply OH spacing.
PLANS/APPL TAKEN TO FRONT DESK  2/7/2002 DONE
DetailsBill Alexander
3rd floor records storage room sprinkler change to apply OH spacing.
Telephone call  2/7/2002 DONE
permit is ready-no fees per bill/2/7/02/mls
FIR-Aging Inspection2/1/20022/1/20022/1/2002 NR
DetailsTroy Cobbley
work in progress 2/1/2002 8:55:10 AM
INSP-Sprinkler Rough-in/Hydro1/23/20021/23/20021/23/2002PPASS
DetailsTroy Cobbley
hydro test for the 2nd floor T.I. is OK 1/23/2002 4:45:30 PM
INSP-Sprinkler Rough-in/Hydro1/9/20021/9/20021/9/2002PPART
DetailsTroy Cobbley
Added by Inspector: 430 On 1/9/2002 2:15:47 PM Ok to install ceiling tile in rooms with heads cut in at this date. I notified contractor to call for reinspection for all other areas when sprinkler heads are installed
INSP-Final Inspection1/8/20021/8/20021/8/2002PPART
DetailsTroy Cobbley
Third floor hydro test OK. OK to install ceiling tiles. 3rd floor shell system and T.I. hangers OK 1/8/2002 4:04:45 PM
FIR-Aging Inspection1/7/20021/7/20021/7/2002 NR
DetailsTroy Cobbley
work in progress 1/7/2002 3:52:14 PM
Issue and Print Permit  10/8/2001 DONE
Inspection Record Card- Fire10/5/2001 10/5/2001 DONE
Telephone call  10/5/2001 DONE
talked to brad to verify plans are ready
Plan assigned to (Bill)9/27/2001 10/4/2001 DONE
10/4/2001 15:11:12 JWA - activity updated through activity FIRA22 from case FIR01-00522.
Sprinkler Plan Check9/28/2001 10/4/2001 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  10/4/2001 DONE
DetailsBill Alexander
Application received  9/27/2001  
DetailsBill Alexander
Case Summary    DONE