INSP-Final Inspection | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm system finaled. OK for perm occ 11/27/2001 4:47:41 PM
|
DOC - Permit Finaled | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 11/27/2001 4:47:56 PM
|
INSP-Final Inspection | 11/21/2001 | 11/26/2001 | 11/26/2001 | A | CANC |
Troy Cobbley
|
|
|
cancelled by contractor 11/26/2001 9:23:51 AM
|
INSP-Final Inspection | 11/26/2001 | 11/26/2001 | 11/26/2001 | P | FAIL |
Troy Cobbley
|
|
|
provide better access to anti-freeze system, provide lockout for facp breaker, smoke detector over panel does not work, duct detectors do not work, provide enclosure and conduit for power supply 11/26/2001 4:03:40 PM
|
INSP-Final Inspection | 11/20/2001 | 11/21/2001 | 11/21/2001 | P | CANC |
Troy Cobbley
|
|
|
Cancelled by the contractor 11/21/2001 1:49:19 PM
|
INSP-Final Inspection | 11/20/2001 | 11/20/2001 | 11/20/2001 | A | NR |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/20/2001 10:49:09 AM Per Dave Miller with the Boise Fire Dept. its OK to give temp on fire alarm system
|
Issue permit | | | 11/20/2001 | | DONE |
|
|
|
|
Alarm Plan Check | | | 11/20/2001 | | PASS |
|
|
|
Resubmttal acceptable.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2001 | | PASS |
|
|
|
|
Inspection Record Card- Fire | 11/20/2001 | | 11/20/2001 | | DONE |
|
|
|
|
Telephone call | | | 11/20/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Telephone call | | | 11/15/2001 | | PEND |
|
|
|
Telcon with Bob Indries,Northwest Industires, a sub-contractor for Big 5. ADT has not responded to our Denied review comments of 11/1, which had 8 items requiring revision. I therefore denied his request for permission to start work without approved plans on site. I also called ADT to follow-up on status, left voice message for Matt Fowler.
|
Telephone call | | | 11/15/2001 | | PEND |
|
|
|
Telcon from Richard Smith, Big % Dir of Const.. He understands the delay creatd by ADT. Refeered him to DM for approval of watchman or other alternate paln until supervision is provided in lieu of alarm service for TOC to open on 11/20.
|
Alarm Plan Check | | | 11/11/2001 | | FAIL |
|
|
|
review faxed to ADT.
|
Telephone call | | | 11/1/2001 | | DONE |
|
|
|
Inspector reports this pm, that installation of the alarm system has begun with the FACP panel, back boxes, wiring pulled, etc.
He will tell General Contractor to stop work. The $100 additional fee will apply to the permit for work without a permit.
|
Plan assigned to (SAM) | 10/18/2001 | | 10/29/2001 | | DONE |
|
|
|
10/29/2001 10:57:53 JWA - activity updated through activity FIRA22 from case FIR01-00564.
|
Application received | | | 10/18/2001 | | |
|
|
|
|