Alarm Plan Check | 1/9/2002 | | 11/11/2002 | | PASS |
|
|
|
Revised 2nd resubmittal is acceptable.
|
INSP-Final Inspection | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 1/30/2002 3:23:34 PM
|
DOC - Permit Finaled | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 1/30/2002 3:25:21 PM
|
Issue and Print Permit | | | 1/14/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/11/2002 | | 1/11/2002 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2002 | | DONE |
|
|
|
talked to john to verify plans are ready
|
Plan assigned to (SAM) | 12/11/2001 | | 1/11/2002 | | DONE |
|
|
|
1/11/2002 15:42:53 SLR - activity updated through activity FIRA22 from case FIR01-00619.
|
Meeting | | | 1/4/2002 | | DONE |
|
|
|
Meeting with Apex, ADS, Petra and owner to discuss the FA revisions necessary. All issues resolved. ADS to redraw plans with necessary revisions, not using plans with Apex's PE stamp on them, and resubmit.
|
Alarm Plan Check | | | 12/21/2001 | | FAIL |
|
|
|
Repalcing a FAC panel installed at the shell stage. Plan submittal information inadequate for review. Comments discussed with John Lopex, ADS.
|
Application received | | | 12/11/2001 | | |
|
|
|
|
Alarm Plan Check | 12/27/2001 | | | | FAIL |
|
|
|
resubmittal did not address review comments. Meeting scheduled for 1/4/02 with designer, vendor, sprinkler contractor, electrician and owner to get all parties to coordinate plans as necessary.
|