DOC - Permit Finaled | 2/4/2003 | 2/4/2003 | 2/4/2003 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 2/4/2003 4:06:14 PM
|
INSP-Final Inspection | 3/5/2002 | 3/6/2002 | 3/6/2002 | A | PASS |
Rick Jackson
|
|
|
deliah ###-####-fn fire -re-insp
|
INSP-Final Inspection | 3/1/2002 | 3/4/2002 | 3/4/2002 | P | FAIL |
Rick Jackson
|
|
|
need audilbe in Nextel from system alarm 3/4/2002 4:49:26 PM
|
INSP-Alarm Testing | 3/1/2002 | 3/4/2002 | 3/4/2002 | P | FAIL |
Rick Jackson
|
|
|
###-#### need battery trouble reporting 3/4/2002 4:49:54 PM
|
Issue permit | | | 2/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/8/2002 | | 2/8/2002 | | DONE |
|
|
|
|
Telephone call | | | 2/8/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Alarm Plan Check | 1/30/2002 | | 2/7/2002 | | PASS |
|
|
|
resubmittal adequate for approval.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/7/2002 | | 2/7/2002 | | DONE |
|
|
|
2/7/2002 16:35:28 SLR - activity updated through activity FIRA22 from case FIR02-00007.
|
Alarm Plan Check | 1/23/2002 | | 1/23/2002 | | FAIL |
|
|
|
per telcon with Stephanie, Simplex, owner wants to utilize a separate releasing panel. DENIED Review comments faxed to Simplex today, with a resubmittal requirement for revised plans for proper releasing panel arrangement. CONDITIONAL APPROVAL IS GRANTED TO ALLOW FIELD INSTALLATION TO BEGIN PRIOR TO RECEIVING THE REQUIRED RESUBMITTAL. Approval to connect the Nextel preaction system will not be given until the required resubmittal has been received and approved.
|
Alarm Plan Check | | | 1/18/2002 | | FAIL |
|
|
|
Plans include an incorrect interconnection to release the Preaction sprinkler system in the new Nextel cellular transmission penthouse building.
Called Simplex and discussed withStephanie. She will have the designer call back to discuss this with me. Written review comments are being held, pending the call from the designer to discuss them.
|
Application received | | | 1/7/2002 | | |
|
|
|
|