Permit Information
Permit NumberFIR02-00010
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 10008 W EMERALD ST
Project NameSPR ALBERTSON'S DATA CENTER
Customer Number 
ePlanReview 
Description
ALBERTSON DATA CENTER - TO INSTALL A MODIFIED LIGHT HAZARD OCCUPANCY FIRE SPRINKLER SYSTEM A IN A NEW 32,880 FT/2, ONE STORY, OFFICE AND DATA STORAGE BUILDING, CONSTRUCTED OF CONCRETE TILT-UP EXTERIOR WALLS WITH STEEL STRUCTURAL INTERIOR COLUMNS AND GIRDERS AND A STEEL ROOF JOISTS WITH METAL ROOF DECK AND BUILT-UP ROOFING SYSTEM. INTERIOR NONBEARING WALLS, TWO RESTROOMS, A 1-HR CORRIDOR, 2-HR WALLS, 1-HR WALLS, ACCESS FLOOR SYSTEMS, SUSPENDED CEILINGS, AND A UNISTRUT GRID, SUSPENDED FROM ROOF JOISTS. THIS BUILDING REQUIRES FULL FIRE SPRINKLER PROTECTION FOR ALLOWABLE BUILDING AREA INCREASE. ALL FIRE SPRINKLER WORK PER RED-LINED NOTES, ATTACHED PLAN REVIEW COMMENTS AND CONDITIONS, AS REGULATED BY FIRE DEPARTMENT, WHICH COMPRISES AND BECOMES A PART OF THE APPROVED PLANS. A FIRE "INSPECTION CARD" IS REQUIRED AS A CONDITION OF THIS PERMIT, TO PROVIDE WITNESS COMPLIANCE WITH ADOPTED CODES & ORDINANCES. UNDERGROUND FIRE LINE INSTALLED UNDER: FIR01-00557. THIS FACILITY WAS BUILT UNDER(SHELL) PERMIT: BLD01-01995. THIS PERMIT IS ATTACHED TO THE BUILDING TENANT IMPROVEMENT PERMIT: BLD01-02601.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/22/20028/22/20028/22/2002APASS
DetailsTroy Cobbley
fire sprinkler finaled
DOC - Permit Finaled8/22/20028/22/20028/22/2002APASS
DetailsTroy Cobbley
Finaled by inspector at 8/22/2002 9:11:54 AM
INSP-Sprinkler Rough-in/Hydro8/7/20028/7/20028/7/2002APASS
DetailsTroy Cobbley
hydro test for system 2 OK 8/7/2002 4:01:38 PM
INSP-Sprinkler Rough-in/Hydro8/5/20028/6/20028/6/2002PFAIL
DetailsTroy Cobbley
hydro test for system 2 failed. gauge was at 209 and after two hours was at 207 lbs 8/6/2002 3:08:54 PM
INSP-Sprinkler Rough-in/Hydro7/22/20027/22/20027/22/2002PPASS
DetailsTroy Cobbley
above ground hydro test for system 1 OK 7/22/2002 3:34:22 PM
INSP-Sprinkler Rough-in6/7/20026/7/20026/7/2002APASS
DetailsTroy Cobbley
rough-in for building OK
INSP-Supply line flush5/28/20025/29/20025/29/2002APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 05/28/2002 at 13:26:41. Contact: ###-####. see permit FIR01-00557; underground complete and doc finaled 5/29/2002 10:39:57 AM
INSP-Sprinkler Rough-in5/2/20025/3/20025/3/2002APASS
DetailsTroy Cobbley
sprinkler piping OK to cover in rooms next to restroom and in main lobby 5/3/2002 12:29:48 PM
Issue and Print Permit  2/26/2002 DONE
Sprinkler Plan Check2/22/2002 2/25/2002 PASS
DetailsBill Alexander
Updated plan requirements (asbuilts), to be attached to origignals.
PLANS/APPL TAKEN TO FRONT DESK  2/25/2002 DONE
DetailsBill Alexander
Telephone call  2/25/2002 DONE
left mess that permit is ready
Issue permit  1/16/2002 DONE
Plan assigned to (Bill)1/9/2002 1/15/2002 DONE
1/15/2002 13:11:06 JWA - activity updated through activity FIRA22 from case FIR02-00010.
PLANS/APPL TAKEN TO FRONT DESK  1/15/2002 DONE
DetailsBill Alexander
Inspection Record Card- Fire1/15/2002 1/15/2002 DONE
Inspection Record Card- Fire1/15/2002 1/15/2002 DONE
Telephone call  1/15/2002 DONE
Sprinkler Plan Check1/9/2002 1/14/2002 DONE
DetailsBill Alexander
Requires asbuilt prior to sign off of permit for verification of 3 items listed in the review notes.
Application received  1/9/2002  
Case Summary    DONE