INSP-Final Inspection | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | PASS |
Troy Cobbley
|
|
|
fire sprinkler system finaled
|
DOC - Permit Finaled | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 9/26/2002 2:56:21 PM
|
INSP-Final Inspection | 9/24/2002 | 9/24/2002 | 9/24/2002 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/24/2002 at 10:45:28. Contact: ###-####. tested tampers/flows okay; need chain/lock on PIV; splash gaurd at inspectors test as shown on plans 9/24/2002 3:13:11 PM
|
INSP-Sprinkler Rough-in | 7/10/2002 | 7/10/2002 | 7/10/2002 | A | FAIL |
Troy Cobbley
|
|
|
All items on the correction notice for the dry system rough-in have been corrected except for protection that needs to be provided in the overbuild areas above the riser room
|
INSP-Sprinkler Rough-in | 6/7/2002 | 6/7/2002 | 6/7/2002 | A | PART |
Troy Cobbley
|
|
|
wet system rough-in ok. Only a small section of the attic dry system was inspected. It had multiple problems so no other areas were looked at. Problems included sprinkler heads spaced too close, heads too far from deck, missing earth quake bracing and head overspaced off of a draft stop and installation of sprinklers in the hydraulic calc area not per plan. I left comment for that area to be resubmitted for Bill Alexanders approval
|
INSP-Sprinkler Rough-in | 6/4/2002 | 6/4/2002 | 6/4/2002 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/4/2002 10:27:15 AM okay to cover sanctuary only; fire treated plywood used
|
INSP-Sprinkler Rough-in | 5/8/2002 | 5/8/2002 | 5/8/2002 | A | PART |
Troy Cobbley
|
|
|
Restrooms located in northwest corner of buildings ok to cover
|
Inspection Record Card- Fire | 3/22/2002 | | 3/22/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/22/2002 | | DONE |
|
|
|
jeff
|
Issue and Print Permit | | | 3/22/2002 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/13/2002 | | 3/21/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2002 | | DONE |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 2/7/2002 | | 3/21/2002 | | DONE |
Bill Alexander
|
|
|
3/21/2002 15:26:35 JWA - activity updated through activity FIRA22 from case FIR02-00039.
|
Miscellaneous action | | | 2/15/2002 | | DONE |
|
|
|
Took rejected plans to front desk for calling and return.
|
Sprinkler Plan Check | 2/7/2002 | | 2/15/2002 | | FAIL |
Bill Alexander
|
|
|
Many areas lack correct fire sprinkler coverage. Remote test #1, dry system attic appears to not be accurate and need reverification.
|
Application received | | | 2/6/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|