INSP-Final Inspection | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinklers finaled
|
DOC - Permit Finaled | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 4/30/2002 12:08:25 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2002 | 4/2/2002 | 4/2/2002 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in OK. Spoke with contractor about sprinkler head temp. at the unit heater. They are to verify. 4/2/2002 2:27:07 PM
|
Inspection Record Card- Fire | 2/25/2002 | | 2/25/2002 | | DONE |
|
|
|
|
Telephone call | | | 2/25/2002 | | DONE |
|
|
|
LEFT MESSAGE PLANS READY//AIM
|
Issue permit | | | 2/25/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 2/14/2002 | | 2/25/2002 | | DONE |
|
|
|
2/25/2002 11:12:18 JWA - activity updated through activity FIRA22 from case FIR02-00050.
|
Sprinkler Plan Check | 2/14/2002 | | 2/25/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2002 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 2/14/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|