DOC - Permit Finaled | 8/26/2002 | 8/26/2002 | 8/26/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 8/26/2002 9:20:39 AM
|
INSP-Final Inspection | 8/20/2002 | 8/23/2002 | 8/23/2002 | A | PASS |
Troy Cobbley
|
|
|
fire alarm system finaled 8/26/2002 9:20:33 AM
|
INSP-Final Inspection | 8/13/2002 | 8/15/2002 | 8/15/2002 | A | FAIL |
Troy Cobbley
|
|
|
test duct detectors and provide a D113 module for the fire alarm panel 8/15/2002 11:45:10 AM
|
INSP-Final Inspection | 7/24/2002 | 7/26/2002 | 7/26/2002 | P | CANC |
Troy Cobbley
|
|
|
cancelled by contractor 7/26/2002 1:20:43 PM
|
Issue permit | | | 6/5/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/4/2002 | | 6/4/2002 | | DONE |
|
|
|
|
Telephone call | | | 6/4/2002 | | DONE |
|
|
|
|
Alarm Plan Check | 6/3/2002 | | 6/3/2002 | | PASS |
Sam Rogers
|
|
|
Plans approved with conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2002 | | DONE |
Sam Rogers
|
|
|
|
Alarm Plan Check | 5/21/2002 | | 5/22/2002 | | HOLD |
|
|
|
Resubmittal of 5/21/02 is acceptable however, the three different smoke detector cut sheets have beeen submitted and the latest one does not match the detector shown on plans. Also two partial sets of cut sheets have been submitted. Discussed with Tom at Mtn Alarm and they will have someone come to office to revise and resubmit plans. Discussed with Tom at Mtn Alarm and they will have someone come to office to revise and resubmit plans. Plans are being held pending resolution by Moutain Alarm.
|
Alarm Plan Check | 4/30/2002 | | 5/10/2002 | | FAIL |
|
|
|
resubmittal of 4/30/02 did not include all all previouosly requested information.
|
Alarm Plan Check | | | 4/23/2002 | | FAIL |
|
|
|
Incomplete information resubmitted. Revised comments faxed to Mtn. Alarm.
|
Alarm Plan Check | | | 3/26/2002 | | FAIL |
|
|
|
review comments faxed to Mountain Alarm. Discussed some items by phone with Frank Bradbury, Mtn Alarm.
|
Application received | | | 3/11/2002 | | |
|
|
|
|