INSP-Final Inspection | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 6/6/2002 3:02:08 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/15/2002 | 5/15/2002 | 5/15/2002 | P | PART |
Rick Jackson
|
|
|
hydro- rick -###-#### hydro test only - pass; plans not available and alarms not ready to test 5/15/2002 12:35:31 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2002 | 5/9/2002 | 5/9/2002 | P | CANC |
Troy Cobbley
|
|
|
###-#### rick
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2002 | 4/15/2002 | 4/15/2002 | P | PASS |
Troy Cobbley
|
|
|
hydro test ok. rough-in for outside canopy and barrel area ok for cover 4/15/2002 3:37:19 PM
|
Sprinkler Plan Check | 3/29/2002 | | 4/9/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2002 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 4/9/2002 | | 4/9/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2002 | | DONE |
|
|
|
CALLED AND LEFT MESSAGE PLANS READY 4-8-02 ///DLD
|
Issue permit | | | 4/9/2002 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/28/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/27/2002 | | 3/27/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/27/2002 | | DONE |
|
|
|
CALLED AND LEFT MESSAGE THAT PLANS ARE READY 3-27-02 ///DLD
|
Plan assigned to (Bill) | 3/19/2002 | | 3/27/2002 | | DONE |
|
|
|
3/27/2002 13:57:54 JWA - activity updated through activity FIRA22 from case FIR02-00099.
|
Sprinkler Plan Check | 3/19/2002 | | 3/27/2002 | | PART |
Bill Alexander
|
|
|
Requires backflow prevention which will include system reverification (hydraulics). Work may proceed on all areas not associated with aniti-freeze system (excluding the removal and replacing of lines from anit-freeze to wet). Will require resubmittal of complete plans and calculations.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2002 | | DONE |
Bill Alexander
|
|
|
1st Submittal
|
Application received | | | 3/19/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|