INSP-Final Inspection | 5/24/2002 | 5/24/2002 | 5/24/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 5/24/2002 12:55:57 PM
|
DOC - Permit Finaled | 5/24/2002 | 5/24/2002 | 5/24/2002 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 5/24/2002 12:57:43 PM
|
INSP-Conference | 5/20/2002 | 5/20/2002 | 5/20/2002 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 5/20/2002 3:43:19 PM met with Terry and he provided the test data on the Victaulic manifold; it appears to be tested with a control valve and 90 degree elbow and it appears to meet criteria as installed
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2002 | 5/17/2002 | 5/17/2002 | P | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 5/17/2002 9:05:59 AM hydro test okay; need flow switch and tamper control valve on hose station as indicated on approved plans; flow switch within 24 inches of control valve; awaiting alarm installation and testing; outside bell not installed 5/17/2002 3:51:24 PM
|
Override - Parcel Holds | | | 5/1/2002 | | |
|
|
|
|
Issue permit | | | 5/1/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 4/12/2002 | | 4/30/2002 | | DONE |
Bill Alexander
|
|
|
4/30/2002 13:39:11 JWA - activity updated through activity FIRA22 from case FIR02-00143.
|
Sprinkler Plan Check | 4/25/2002 | | 4/30/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2002 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 4/30/2002 | | 4/30/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/30/2002 | | DONE |
|
|
|
CALLED LEFT V-MESSAGE FOR JOHN PLANS READY 4-29-02 ///DLD
|
Telephone call | | | 4/24/2002 | | DONE |
|
|
|
plans denied will pick up
|
Sprinkler Plan Check | 4/12/2002 | | 4/23/2002 | | FAIL |
Bill Alexander
|
|
|
High piled storage system protection with ordinary hazard design.
|
Miscellaneous action | | | 4/23/2002 | | DONE |
|
|
|
Took denied plans to front desk for returning.
|
Application received | | | 4/12/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|